R-01: Project Setup Validation Report
Data Date: 28 Feb 2026
Project Setup Validation Report
Pre-Baseline Quality Audit — Sunrise Refinery Turnaround
ProjectSunrise Refinery T/A 2026
Data Date28 Feb 2026
Audit StagePre-Baseline BL0
SchedulerA. Khalid, PSP
P6 Project IDSR-TA-2026-001
Total Activities
10,247
Incl. 312 milestones
Open-Ended Activities
15
Dangling predecessors/successors
Hard Constraints
8.2%
841 activities constrained
Missing Calendars
4
Resources without calendar
Negative Float
23
Activities with TF < 0
74 /100

Schedule Quality Score: CONDITIONAL PASS

3 checks failed, 2 warnings issued. Recommend corrective action on hard constraints and negative float prior to baseline sign-off. Open-ended activities must be resolved before BL0 is locked.

3 FAIL  2 WARN  5 PASS
Quality Checklist — 10 Metrics
# Check Description Threshold Actual Metric Status Finding
1 Open-ended activities (no predecessor) = 0 8 Count FAIL Missing predecessors on 8 Level-3 activities
2 Open-ended activities (no successor) ≤ 1 7 Count FAIL Multiple dead-end paths in Process Units area
3 Hard constraint usage rate ≤ 5% 8.2% % FAIL 841 MSO/MFO/SNET constraints. Exceeds 5% tolerance.
4 Activities with negative total float = 0 23 Count WARN 23 activities with TF between -1d and -8d
5 Resources without assigned calendar = 0 4 Count WARN Welding Inspector, QC Lead, Safety Officer, Document Controller
6 Activities without resource assignment ≤ 2% 1.4% % PASS 143 unresourced (admin & procurement activities, acceptable)
7 Activity duration > 20 working days ≤ 5% 2.1% % PASS 215 activities. Majority are procurement long-leads.
8 Out-of-sequence progress recorded = 0 0 Count PASS No out-of-sequence progress. Project not yet started.
9 Logic density (relationships / activities) ≥ 1.5 1.82 Ratio PASS 18,649 relationships total. Good network density.
10 Baseline approved and saved = YES NO Y/N PASS Pre-baseline audit — expected. BL0 pending client sign-off.

Thresholds per DCMA 14-Point Assessment and client schedule specification Rev 3.

Failing Detail — Open-Ended Activities (15 total)
Activity ID Activity Name WBS Duration Issue Recommended Fix
A1020 Isolate Crude Distillation Unit (CDU-1) SR.PU.CDU 2d No Predecessor Link to A1010 Safety Walk-down Complete
A1035 Scaffold Erection — CDU Overhead SR.PU.CDU 3d No Predecessor FS link from A1020 Isolation
B2150 Blind Flange Installation — Heat Exchanger Train SR.PU.HX 1d No Predecessor Predecessor from B2140 P&ID mark-up sign-off
C3004 Catalyst Unloading — Reactor R-101 SR.REACT 5d No Predecessor Depends on nitrogen purge C3001
E5820 Final Punch List Clearance — Area 5 SR.AREA5 4d No Successor Add FS to E5830 Pre-commissioning Handover
E5821 Final Punch List Clearance — Area 6 SR.AREA6 4d No Successor Add FS to E5830 Pre-commissioning Handover
F6010 Hydrostatic Test — Fuel Gas Header SR.PIPE 2d No Successor Link to F6020 Pressure Reinstatement
G7200 Electrical Loop Check — Substation 4 SR.ELEC 3d No Successor Add FS to G7210 MCC Energisation
H8305 Instrument Calibration — Flow Meters FT-201–240 SR.INST 6d No Successor Link to H8400 Instrument Acceptance Sign-Off

Showing 9 of 15 open-ended activities. Full list available in Appendix A.

Hard Constraint Sample — Top Offenders
Activity ID Activity Name Constraint Type Constraint Date Float (d) Justification
M0010 Unit Ready for Restart — Milestone MFO 15 Apr 2026 0 Contractual completion date. Acceptable.
A3300 Decoking — Furnace F-101 MSO 10 Mar 2026 -3 No justification in schedule. Remove constraint.
B2200 Tube Bundle Pulling — E-201 MSO 12 Mar 2026 -5 Maintenance window — discuss with operations.
D4100 Crane Lift — Deethaniser Column SNET 22 Mar 2026 4 Specialist crane availability. Document in memo.
G7010 Switchgear Maintenance — SG-01 SNET 01 Mar 2026 8 OEM engineer availability window. Acceptable.
Auditor's Recommendation

The schedule passes 5 of 10 checks and has 2 warnings requiring minor corrective action. Three items represent a formal FAIL status that must be resolved before BL0 is accepted by the client:

  1. Open-ended activities (15 total): Assign missing predecessors and successors. Target: all resolved within 3 working days.
  2. Hard constraint rate (8.2%): Reduce to below 5% by replacing unjustified MSO constraints with proper logic. 650+ constraints should be removable.
  3. Negative float (23 activities): Investigate driving path and compress or re-sequence to clear negative float before baseline lock.

Re-audit scheduled for 07 Mar 2026. Baseline sign-off meeting with client: 10 Mar 2026.