R-02: Baseline Summary Report
Data Date: 28 Feb 2026
Baseline Summary Report — BL1
Harbor Bridge Replacement Project — Government Infrastructure Program
ProjectHarbor Bridge Replacement
BaselineBL1 — Approved 01 Feb 2026
Total Budget (BL)$340,200,000
BL Start15 Jan 2026
BL Finish14 Jan 2029
Duration36 months
Total Activities (BL)
4,892
Incl. 145 milestones
WBS Level 2 Nodes
8
Discipline branches
Total Budget (BAC)
$340.2M
Excl. contingency $28M
Contractual Milestones
12
LD-bearing milestones
Critical Path Duration
1,096d
Float = 0d on CP
WBS Level 2 — Baseline Cost & Schedule Summary
WBS Code WBS Name Resp. Manager Activities Milestones BL Start BL Finish BL Budget % Budget
HBR.10 Project Management & Controls S. Nguyen 248 18 15 Jan 2026 14 Jan 2029 $18,400,000 5.4%
HBR.20 Civil Works — Abutments & Approaches R. Petrov 612 14 01 Apr 2026 30 Sep 2027 $54,600,000 16.0%
HBR.30 Substructure — Piers & Caissons J. Okafor 487 22 15 Mar 2026 31 Aug 2027 $71,200,000 20.9%
HBR.40 Superstructure — Main Bridge Span M. Lindqvist 734 28 01 Sep 2027 30 Jun 2028 $98,400,000 28.9%
HBR.50 Electrical, Lighting & ITS P. Sharma 318 16 01 Jul 2028 30 Sep 2028 $22,800,000 6.7%
HBR.60 Waterworks & Environmental Controls K. Andersson 291 11 15 Apr 2026 31 Mar 2027 $19,600,000 5.8%
HBR.70 Traffic Management & Diversions D. Walsh 204 19 15 Jan 2026 14 Jan 2029 $14,200,000 4.2%
HBR.80 Testing, Commissioning & Handover F. Ibrahim 212 17 01 Oct 2028 14 Jan 2029 $41,000,000 12.1%
PROJECT TOTAL 4,892 145 15 Jan 2026 14 Jan 2029 $340,200,000 100%
Key Project Milestones
Milestone ID Milestone Name Type BL Date LD Rate Status
MS-001 Notice to Proceed Issued Contractual 15 Jan 2026 Achieved
MS-005 All Permits Received Internal 01 Apr 2026 In Progress
MS-020 Substructure Works Complete Contractual 31 Aug 2027 $15,000/day Future
MS-035 Main Span Bridge Deck Complete Contractual 30 Jun 2028 $25,000/day Future
MS-050 Bridge Open to Traffic Strategic 14 Jan 2029 $50,000/day Future

WBS HBR.40 — Superstructure: Main Bridge Span (Sample Detail Page)

Budget: $98,400,000 | 734 Activities
BL Early Start 01 Sep 2027
BL Early Finish 30 Jun 2028
BL Late Finish 30 Jun 2028
Total Float 0d (Critical)
Duration (BL) 305 days
Responsible M. Lindqvist
Cost Account Description Activities BL Budget % of Node
HBR.40.10 Falsework & Temporary Works 82 $8,200,000 8.3%
HBR.40.20 Precast Girder Supply & Installation 156 $31,500,000 32.0%
HBR.40.30 In-Situ Concrete — Bridge Deck 204 $22,400,000 22.8%
HBR.40.40 Structural Steelwork — Arch Ribs 168 $28,300,000 28.8%
HBR.40.50 Surfacing, Barriers & Joints 124 $8,000,000 8.1%
WBS HBR.40 Total 734 $98,400,000 100%

Resource Summary — Peak Period (Q1 2028)

142
Peak Workforce
18
Crane Lifts
4
Mobile Cranes
8,640t
Concrete Volume
Scope Description

WBS HBR.40 covers all structural works for the 420m main river span including erection of 6 precast box girder spans, in-situ reinforced concrete bridge deck, twin arch ribs (structural steel Grade S460), hanger cables, surfacing, expansion joints, and edge protection. This is the critical path element governing overall project completion. Any delay to this node will directly impact the Bridge Open to Traffic milestone (MS-050).

Baseline Approval — BL1
Project Manager
S. Nguyen, PMP
Date: ____________________
Client Representative
City Infrastructure Dept.
Date: ____________________
Project Controls Manager
F. Ibrahim, EVP
Date: ____________________