Field / Site Dashboard — Al Rayyan Highway Zone B
Foreman View · Week of 02 Mar 2026 · Generated: 01 Mar 2026 05:30 AM
Activities This Week
12
7 starting · 5 continuing
Activities Next Week
8
3 start-ups planned
Blocked
5
3 permit · 2 material wait
Crew On Site
47
Plan: 52 · shortage: 5
Physical % Zone B
58%
BL: 62% (−4 pts behind)
Weather Days Lost
3
This month (high wind)
Civil
Bridge Deck Pour Seg 4
Civil
Formwork Removal Z-3
Struct
Rebar Install Seg 5 🔒
BLOCKED — Rebar delivery pending
Civil
Concrete Curing Z-2
11d curing · auto-monitored
Civil
Safety Fence Install 🔒
Civil
Drainage Layer Wk 2
In Progress / On Track
Planned / Not Started
At Risk
Critical / Blocked
Weekend
Formwork Removal Z-3
✅
✅
✅
✅
Concrete Curing Z-2
✅
✅
✅
✅
Rebar Install Seg 5
✅
❌
✅
✅
Safety Fence Install
✅
✅
❌
✅
Drainage Layer Wk 2
✅
✅
✅
⚠️
Road Sub-base Layer A
❌
❌
❌
✅
Guardrail Foundation A
✅
✅
✅
✅
Survey Setout Wk 2
✅
✅
✅
✅
Ready: 3
Blocked: 3
Watch: 1
Concreters
12
12
8
8
10
8
Steel Fix.
8
8
10
6
6
10
Carpenters
6
6
4
4
4
4
Surveyors
2
2
2
2
2
3
Gen. Labor
8
8
7
7
7
6
Total
36
36
31
27
29
31
Plan: 52 crew on site · Actual: 47 · Shortage: 5 (3 absent sick, 2 crew mobilizing from Zone A)
Project overall: 38.6% physical complete
Blockers: 3× RTA Work Permits · 1× Rebar shortage · 1× Concrete pump breakdown