Project: Greenfield Combined Cycle Power Plant ▾
Data Date: 28 Feb 2026
BN
Category: All Packages Long-Lead Bulk Materials Subcontracts Status: All Active On Track At Risk

Contract & Procurement Dashboard — Greenfield Combined Cycle Power Plant

24 Active Packages · Generated: 01 Mar 2026 08:15 AM
Active Packages
24
$480M total commitment
On Track
18
75% of packages
At Risk
4
Delivery slippage <30d
Critical
2
Driving project end date
Longest Lead Time
18 mo
Gas turbine assembly
CP Procurement
3
Items on critical path
Procurement Pipeline — Top 8 Packages (Stage-Gate) All 24 Packages →
Requisition
RFQ Issued
Evaluation
PO Issued
Fabrication
Shipping
Delivered
Gas Turbine
Active
Jun
Sep
Fab
HRSG
Active
Jul
Oct
Fab
Steam Turbine
Late
Apr
Aug
Nov
At Risk
Main Transformer
Late
Mar
May
Sep
Nov
Critical
Cooling Tower
Transit
Apr
On Track
Condenser Pkg
Active
May
Jun
On Track
HV Switchgear
Hold
Apr
Jun
Oct
Dec
Critical
Instrumentation
Open
Mar
Apr
Jun
Sep
Nov
On Track
✓ Complete  |  ■ Active  |  ! At Risk  |  ✕ Critical / Hold  |  □ Pending
Long-Lead Items
Item PO Date Exp. Delivery LT (mo) Status
Gas Turbine (GT1) 15 Mar 25 15 Sep 26 18 Fab
HRSG Unit (H1) 1 May 25 1 Sep 26 16 Fab
Steam Turbine (ST1) Nov 2026 14 PO Pending
Main Transformer Nov 2026 12 Critical
HV Switchgear Dec 2026 10 Critical
Cooling Tower 20 Jun 25 Apr 2026 10 Transit
Contractual Milestone Compliance Contract Register →
Milestone Contract Date Forecast Var (d) Status
Site Possession 1 Nov 2025 1 Nov 2025 0 Met
Civil Mobilization 15 Dec 2025 15 Dec 2025 0 Met
Gas Turbine PO Placement 15 Mar 2025 15 Mar 2025 0 Met
Foundation Complete — GT1 28 Feb 2026 28 Feb 2026 0 Met
Steam Turbine PO Placement 1 Mar 2026 25 Mar 2026 +24 At Risk
Main Transformer PO Placement 28 Feb 2026 15 Apr 2026 +45 Critical
GT1 Ready for Erection 15 Sep 2026 15 Sep 2026 0 Forecast
Mechanical Completion 31 Jan 2027 28 Feb 2027 +28 Watch
Supplier Performance Supplier Portal →
Supplier Pkgs On-Time % Quality Rating
Siemens Energy (GT) 1 100% 9.2/10 Preferred
BABCOCK HRSG Ltd. 1 95% 8.8/10 Approved
ABB Transformers 2 72% 8.4/10 Conditional
Schneider Electric 3 78% 8.1/10 Conditional
Doosan Heavy Ind. 1 88% 8.6/10 Approved
Local Steel Fabricator A 4 91% 7.6/10 Approved
GlobeCivil Works Ltd. 5 61% 7.2/10 Probation
Procurement Critical Path — Items Driving Schedule End Date Schedule Impact Analysis →
Item Supplier Required On Site Forecast On Site Float (d) Schedule Impact Mitigation Owner Status
Main Transformer (T1) ABB Transformers 1 Nov 2026 15 Dec 2026 −45 +45d commissioning delay if not resolved Expedite — visit factory 15 Mar Procurement Mgr Critical
HV Switchgear (132kV) Schneider Electric 15 Nov 2026 20 Dec 2026 −35 Blocks energization sequence Split order — use temporary switchgear Procurement Mgr Critical
Steam Turbine (ST1) TBD — Evaluation 1 Oct 2026 25 Oct 2026 −24 May delay combined cycle test Accelerate evaluation; PO by 25 Mar Engineering Mgr At Risk
Current procurement delay exposes project to 45-day schedule overrun and potential liquidated damages of $2.25M (per contract clause 14.3 @ $50K/day).
Factory expedite visit for Main Transformer scheduled 15 Mar 2026. Recovery potential: 20–30 days if manufacturer agrees to premium shift work.