Project: Al Rayyan Highway — Zone B ▾
Data Date: 28 Feb 2026
AM
Zone: Zone B Zone A Zone C Zone D Trade: All Trades Civil Structural MEP Week: Current + 1

Field / Site Dashboard — Al Rayyan Highway Zone B

Foreman View · Week of 02 Mar 2026 · Generated: 01 Mar 2026 05:30 AM
Activities This Week
12
7 starting · 5 continuing
Activities Next Week
8
3 start-ups planned
Blocked
5
3 permit · 2 material wait
Crew On Site
47
Plan: 52 · shortage: 5
Physical % Zone B
58%
BL: 62% (−4 pts behind)
Weather Days Lost
3
This month (high wind)
2-Week Lookahead — Simplified Gantt (Zone B) Full Schedule →
Mon
2
Tue
3
Wed
4
Thu
5
Fri
6
Sat
7
Sun
8
Mon
9
Tue
10
Wed
11
Thu
12
Fri
13
Sat
14
Sun
15
Civil Bridge Deck Pour Seg 4
▶ 62% — RD:17d
Civil Post-Tension Prep
Pre-stress Equip Ready
Civil Formwork Removal Z-3
3d
Struct Rebar Install Seg 5 🔒
BLOCKED — Rebar delivery pending
Civil Concrete Curing Z-2
11d curing · auto-monitored
Civil Safety Fence Install 🔒
PERMIT PENDING (RTA)
Civil Drainage Layer Wk 2
5d — Mon 9–Fri 13
In Progress / On Track Planned / Not Started At Risk Critical / Blocked Weekend
Activity Readiness Check
Activity
Pred
Matl
Perm
Crew
Formwork Removal Z-3
Concrete Curing Z-2
Rebar Install Seg 5
Safety Fence Install
Drainage Layer Wk 2
⚠️
Road Sub-base Layer A
Guardrail Foundation A
Survey Setout Wk 2
Ready: 3 Blocked: 3 Watch: 1
Crew Deployment — Trade × Day (Headcount)
Mon 2
Tue 3
Wed 4
Thu 5
Fri 6
Mon 9
Concreters
12
12
8
8
10
8
Steel Fix.
8
8
10
6
6
10
Carpenters
6
6
4
4
4
4
Surveyors
2
2
2
2
2
3
Gen. Labor
8
8
7
7
7
6
Total
36
36
31
27
29
31
Plan: 52 crew on site · Actual: 47 · Shortage: 5 (3 absent sick, 2 crew mobilizing from Zone A)
Physical % by Zone
72%
A
58%
B
41%
C
28%
D
Project overall: 38.6% physical complete
Daily Progress Summary
Started Today
3
Completed Today
1
% Progress Logged
8 / 12
📋
Blocked Today
5
🔒
Blockers: 3× RTA Work Permits · 1× Rebar shortage · 1× Concrete pump breakdown