Contract & Procurement Dashboard — Greenfield Combined Cycle Power Plant
24 Active Packages · Generated: 01 Mar 2026 08:15 AM
Active Packages
24
$480M total commitment
On Track
18
75% of packages
At Risk
4
Delivery slippage <30d
Critical
2
Driving project end date
Longest Lead Time
18 mo
Gas turbine assembly
CP Procurement
3
Items on critical path
Requisition
RFQ Issued
Evaluation
PO Issued
Fabrication
Shipping
Delivered
Main Transformer
Critical
Instrumentation
✓
Open
Mar
Apr
Jun
Sep
Nov
On Track
✓ Complete |
■ Active |
! At Risk |
✕ Critical / Hold |
□ Pending
| Item |
PO Date |
Exp. Delivery |
LT (mo) |
Status |
| Gas Turbine (GT1) |
15 Mar 25 |
15 Sep 26 |
18 |
Fab |
| HRSG Unit (H1) |
1 May 25 |
1 Sep 26 |
16 |
Fab |
| Steam Turbine (ST1) |
— |
Nov 2026 |
14 |
PO Pending |
| Main Transformer |
— |
Nov 2026 |
12 |
Critical |
| HV Switchgear |
— |
Dec 2026 |
10 |
Critical |
| Cooling Tower |
20 Jun 25 |
Apr 2026 |
10 |
Transit |
| Milestone |
Contract Date |
Forecast |
Var (d) |
Status |
| Site Possession |
1 Nov 2025 |
1 Nov 2025 |
0 |
Met |
| Civil Mobilization |
15 Dec 2025 |
15 Dec 2025 |
0 |
Met |
| Gas Turbine PO Placement |
15 Mar 2025 |
15 Mar 2025 |
0 |
Met |
| Foundation Complete — GT1 |
28 Feb 2026 |
28 Feb 2026 |
0 |
Met |
| Steam Turbine PO Placement |
1 Mar 2026 |
25 Mar 2026 |
+24 |
At Risk |
| Main Transformer PO Placement |
28 Feb 2026 |
15 Apr 2026 |
+45 |
Critical |
| GT1 Ready for Erection |
15 Sep 2026 |
15 Sep 2026 |
0 |
Forecast |
| Mechanical Completion |
31 Jan 2027 |
28 Feb 2027 |
+28 |
Watch |
| Supplier |
Pkgs |
On-Time % |
Quality |
Rating |
| Siemens Energy (GT) |
1 |
100% |
9.2/10 |
Preferred |
| BABCOCK HRSG Ltd. |
1 |
95% |
8.8/10 |
Approved |
| ABB Transformers |
2 |
72% |
8.4/10 |
Conditional |
| Schneider Electric |
3 |
78% |
8.1/10 |
Conditional |
| Doosan Heavy Ind. |
1 |
88% |
8.6/10 |
Approved |
| Local Steel Fabricator A |
4 |
91% |
7.6/10 |
Approved |
| GlobeCivil Works Ltd. |
5 |
61% |
7.2/10 |
Probation |
| Item |
Supplier |
Required On Site |
Forecast On Site |
Float (d) |
Schedule Impact |
Mitigation |
Owner |
Status |
| Main Transformer (T1) |
ABB Transformers |
1 Nov 2026 |
15 Dec 2026 |
−45 |
+45d commissioning delay if not resolved |
Expedite — visit factory 15 Mar |
Procurement Mgr |
Critical |
| HV Switchgear (132kV) |
Schneider Electric |
15 Nov 2026 |
20 Dec 2026 |
−35 |
Blocks energization sequence |
Split order — use temporary switchgear |
Procurement Mgr |
Critical |
| Steam Turbine (ST1) |
TBD — Evaluation |
1 Oct 2026 |
25 Oct 2026 |
−24 |
May delay combined cycle test |
Accelerate evaluation; PO by 25 Mar |
Engineering Mgr |
At Risk |
Current procurement delay exposes project to 45-day schedule overrun and potential liquidated damages of $2.25M (per contract clause 14.3 @ $50K/day).
Factory expedite visit for Main Transformer scheduled 15 Mar 2026. Recovery potential: 20–30 days if manufacturer agrees to premium shift work.