Project Manager Dashboard — Riverside Medical Center
Hospital Construction · 55% Complete · Generated: 01 Mar 2026 08:15 AM
SPI
0.94
▼ 0.01 from last period
CPI
1.01
▲ 0.01 from last period
TCPI
1.03
To complete to BAC
BEI
0.92
Baseline exec. index
EAC
$127.5M
BAC: $126.2M (+1.0%)
% Complete
55%
BL: 58% (−3 pts behind)
| Milestone |
BL Date |
Forecast |
Var (d) |
Status |
| Structural Steel Complete — Blk A |
15 Mar 2026 |
15 Mar 2026 |
0 |
On Track |
| Exterior Cladding Start |
1 Apr 2026 |
8 Apr 2026 |
+7 |
Watch |
| MEP Rough-In — Floors 1–4 |
15 Apr 2026 |
25 Apr 2026 |
+10 |
Watch |
| Interim Handover — ICU Block |
30 Apr 2026 |
20 May 2026 |
+20 |
Critical |
| Roof Waterproofing Complete |
15 May 2026 |
22 May 2026 |
+7 |
Watch |
| Medical Gas System Test |
1 Jun 2026 |
1 Jun 2026 |
0 |
On Track |
| Building Commissioning Start |
1 Aug 2026 |
22 Aug 2026 |
+21 |
Watch |
| Practical Completion |
30 Sep 2026 |
20 Oct 2026 |
+20 |
At Risk |
Starting this week (7)
In Progress (continuing)
Completing
| Act. ID |
Activity Name |
Discipline |
OD |
RD |
TF |
Status |
| RMC-1240 |
MEP Rough-In — ICU Floor 3 |
MEP |
18 |
18 |
−8 |
Critical |
| RMC-1255 |
Medical Gas Rough-In — Blk B |
Mechanical |
14 |
14 |
−5 |
Critical |
| RMC-1310 |
Electrical Conduit — ICU Corridor |
Electrical |
10 |
8 |
−3 |
Critical |
| RMC-1180 |
Concrete Slab — Level 4 |
Civil |
12 |
12 |
2 |
Near-Crit |
| RMC-1195 |
Structural Frame — Wing C |
Structural |
20 |
15 |
3 |
Near-Crit |
| RMC-1360 |
Fire Suppression Install — FL 3 |
MEP |
8 |
8 |
4 |
Near-Crit |
| RMC-1420 |
Curtain Wall — South Facade |
Structural |
22 |
20 |
5 |
Near-Crit |
| RMC-1445 |
BMS Backbone Installation |
Electrical |
15 |
15 |
6 |
Near-Crit |
| RMC-1510 |
Roofing Membrane Application |
Civil |
10 |
10 |
8 |
Monitor |
| RMC-1560 |
Ext. Cladding — North Elevation |
Structural |
25 |
22 |
9 |
Monitor |
Total variance: +20 calendar days. Contractor claim submitted 14 Feb 2026.
Wk−7Wk−6Wk−5Wk−4Wk−3Wk−2Wk−1Now
SPI (0.94)
CPI (1.01)
BAC
$126.2M
BCWS (PV)
$73.2M
BCWP (EV)
$69.4M
ACWP (AC)
$68.7M
SV (Sched. Var.)
−$3.8M
CV (Cost Var.)
+$0.7M
EAC
$127.5M
JulAugSepOctNovDecJanFeb
EAC rising 8 consecutive periods
Current overrun: +$1.3M (1.0%). TCPI 1.03 — achievable if no further cost growth.