Project: Al Rayyan Highway Expansion ▾
Data Date: 28 Feb 2026
SK
WBS Level: All Level 2 Level 3 Status: All Not Started In Progress Complete Baseline: BL3 — Rev C

Planner / Scheduler Dashboard

Al Rayyan Highway Expansion · 1,247 Activities · Last Scheduled: 28 Feb 2026
Total Activities
1,247
+23 since last update
Complete
481
38.6% of total
In Progress
127
10.2% of total
Not Started
639
51.2% of total
Critical Activities
38
3.0%  |  TF ≤ 0
Near-Critical
64
5.1%  |  TF ≤ 10
DCMA Score
10/14
4 warnings · 0 fails
DCMA 14-Point Schedule Assessment Full Report →
1. Logic (Missing) 2.1%
2. Leads 0.0%
3. Lags 6.8% !
4. Relationship Types 14.2%
5. Hard Constraints 7.3% !
6. High Float (>44d) 3.1%
7. Negative Float 1.0%
8. High Duration (>44d) 1.4%
9. Invalid Dates 0.0%
10. Resources Loaded 68.4% !
11. Missed Status 4.2%
12. Critical Path Test PASS
13. CP Length Index 1.09 !
14. BEI 0.92
Thresholds: DCMA standard  |  10 Pass  |  4 Warning  |  0 Fail  · Warnings: Lags >5%, Hard Constraints >5%, Resources <85%, CPLI >1.05
Total Float Distribution Details →
<−10
−10–0
0–10
10–20
20–30
30–50
50–80
80–120
>120
Neg. Float: 38 (3.0%) Near-Crit ≤10d: 64 (5.1%) Healthy >20d: 847 (67.9%)
Activities by WBS Zone
Zone Total Critical Neg. Float Health
Zone A — Earthworks 312 2 0 Good
Zone B — Bridge Struct. 284 18 12 Critical
Zone C — Paving 418 14 5 Watch
Zone D — MEP / Services 233 4 2 Watch
Relationship Types
3,412
Total Rels
FS 2,458 (72%)
SS 512 (15%)
FF 273 (8%)
SF 169 (5%)
Rels with lag >5d: 84  |  Logic density: 2.74
SS+FF as % total
23% SS+FF — DCMA threshold: <25% ✓
Constraint Summary
ASAP 649 (52.0%)
Finish No Later Than 225 (18.0%)
Start Not Earlier Than 150 (12.0%)
Start No Later Than 100 (8.0%)
Mandatory Finish On 75 (6.0%)
Mandatory Start On 48 (4.0%)
Hard constraints (MFO+MSO): 123 (9.9%) — exceeds DCMA 5% threshold
Open-Ended Activities (Missing Logic) Export List →
14
No Predecessor
12
No Successor
3
Neither
DCMA Check (Logic)
2.1%
missing logic < DCMA 5% limit ✓
ID Activity Name WBS Issue Status
A0842 Temporary Works — Dewatering 3.2.1 No Pred In Progress
A1105 Safety Barrier Relocation 4.1.3 No Pred Not Started
A0990 Environmental Monitoring Q2 2.4.1 No Succ In Progress
A1233 Client Furnished Equipment Del. 5.1.2 Neither Not Started
Lag Analysis — Top Offenders All Lags →
Predecessor Successor Type Lag Lag / Succ OD Justification
A0610 A0625 SS 22d 73%
A0815 A0830 SS 18d 60% Curing time
A1120 A1135 FS 15d 50% Inspection hold
A0440 A0458 SS 12d 40%
A0720 A0735 FF 10d 33%
3 relationships have SS+lag >50% of successor OD with no justification — likely masking duration compression. Recommend: convert to FS with reduced lag and re-schedule.
Lag Distribution Summary
68
1–5 Days
11
6–14 Days
5
>14 Days