R-34: As-Built Schedule Report
As-Built Date: 15 Feb 2026
As-Built Schedule Report
Nordic Wind Farm — Phase 2 (Offshore Array) — Final As-Built Record — All Activities 100% Complete
ProjectNordic Wind Farm — Phase 2 Offshore Array
ClientNordic Renewables AS
ContractorFjord Offshore Constructors
Project Start15 Apr 2023
Project Finish28 Jan 2026
As-Built Verified15 Feb 2026
Total Activities
312
All 100% complete
As-Built Duration
34 mo
vs. 33 mo planned (+1 mo)
Final Cost
€312.4M
vs. €318M budget (−1.8%)
Turbines Installed
48
8 MW each — 384 MW total
As-Built Verified
All dates confirmed
As-Built Schedule — Verified
Verification Date: 15 Feb 2026
All Actual Dates Confirmed
Cross-checked vs. Daily Reports & MIR
Final Cost Register Reconciled
As-at 31 Jan 2026 — Accounts Closed
📋
Approved by: E. Bergstrom, PM
Senior Project Manager — 15 Feb 2026
Project Summary Statistics
312
Total Activities
312
100% Complete
8
WBS Level 2 Groups
33d
Avg Actual Duration
Actual Duration Distribution
Number of activities by actual duration range
28
1–5d
47
6–10d
84
11–20d
76
21–30d
52
31–44d
18
45–60d
7
>60d
As-Built Activity Listing — Grouped by WBS, Sorted by Actual Start
WBS Activity ID Activity Name Actual Start Actual Finish Act. Dur. Final % Final Cost (€K) Verified
WBS 01 — Engineering & Design  18 activities
01.01 NWF-0101 Concept Design — Array Layout Optimisation 15 Apr 2023 30 May 2023 35d 100% 420
01.01 NWF-0102 Metocean Study — Site-Specific Wind & Wave Data 15 Apr 2023 14 Jul 2023 63d 100% 890
01.02 NWF-0110 Detailed Design — Monopile Foundation 01 Jun 2023 31 Aug 2023 65d 100% 1,240
01.02 NWF-0115 Detailed Design — Transition Piece & J-Tube 01 Jun 2023 15 Sep 2023 75d 100% 980
01.03 NWF-0120 Electrical Array Cable Route Engineering 01 Jul 2023 30 Sep 2023 65d 100% 760
01.04 NWF-0130 Marine Consent & Environmental Impact Assessment 15 Apr 2023 30 Oct 2023 140d 100% 1,180
WBS 01 — Engineering & Design Subtotal (18 activities) € 11,820K All ✓
WBS 02 — Procurement & Fabrication  24 activities
02.01 NWF-0201 PO Issued — Wind Turbine Generators (48 × 8MW) 01 Jul 2023 01 Jul 2023 1d 100% 192,000
02.02 NWF-0210 PO Issued — Monopile Foundations (48 units) 15 Sep 2023 15 Sep 2023 1d 100% 28,400
02.02 NWF-0215 Monopile Fabrication — Batches 1–3 (16 units each) 15 Nov 2023 30 Jun 2024 160d 100%
02.03 NWF-0220 PO Issued — Inter-Array Cable (34km total) 01 Oct 2023 01 Oct 2023 1d 100% 14,200
02.04 NWF-0230 WTG Factory Acceptance Tests — All Turbines 15 Sep 2024 30 Nov 2024 55d 100% 1,440
WBS 02 — Procurement & Fabrication Subtotal (24 activities) € 81,240K All ✓
WBS 03 — Marine Transport & Monopile Installation  62 activities
03.01 NWF-0301 Mobilise Installation Vessel — Svanen III 01 May 2024 12 May 2024 10d 100% 2,800
03.02 NWF-0310 Transport Monopiles Batch 1 — Port to Site 20 May 2024 26 May 2024 6d 100% 620
03.02 NWF-0315 Monopile Installation — Batch 1 (Positions 01–16) 27 May 2024 30 Jul 2024 44d 100% 6,200
03.02 NWF-0320 Monopile Installation — Batch 2 (Positions 17–32) 05 Aug 2024 02 Oct 2024 44d 100% 6,200
03.02 NWF-0325 Monopile Installation — Batch 3 (Positions 33–48) 10 Oct 2024 06 Dec 2024 44d 100% 6,200
03.03 NWF-0340 Transition Piece Installation — All 48 Positions 02 Aug 2024 22 Dec 2024 102d 100% 5,840
03.04 NWF-0350 Vessel Standby — Weather Window Losses (Documented) 01 May 2024 22 Dec 2024 18d total 100% 7,200
WBS 03 — Marine Transport & Monopile Subtotal (62 activities) € 72,140K All ✓
WBS 04 — Wind Turbine Generator Installation  58 activities)
04.01 NWF-0401 Mobilise WTG Installation Vessel — Bold Tern 15 Nov 2024 25 Nov 2024 10d 100% 3,100
04.02 NWF-0410 WTG Installation — Turbines T01–T12 (Zone A) 28 Nov 2024 20 Jan 2025 38d 100% 4,200
04.02 NWF-0415 WTG Installation — Turbines T13–T24 (Zone B) 28 Jan 2025 22 Mar 2025 39d 100% 4,200
04.02 NWF-0420 WTG Installation — Turbines T25–T36 (Zone C) 01 Apr 2025 22 May 2025 37d 100% 4,200
04.02 NWF-0425 WTG Installation — Turbines T37–T48 (Zone D) 02 Jun 2025 28 Jul 2025 40d 100% 4,200
04.03 NWF-0440 Tower Bolt Tensioning & NDT — All Turbines 20 Jan 2025 10 Aug 2025 Rolling 100% 1,440
WBS 04 — WTG Installation Subtotal (58 activities) € 42,680K All ✓
WBS 05 — Inter-Array Cable Installation  46 activities
05.01 NWF-0501 Mobilise Cable Lay Vessel — Nexans Aurora 15 Mar 2025 22 Mar 2025 7d 100% 1,800
05.02 NWF-0510 Inter-Array Cable Lay — String 1 (T01–T08) 25 Mar 2025 10 Apr 2025 14d 100% 2,140
05.02 NWF-0515 Inter-Array Cable Lay — String 2 (T09–T16) 12 Apr 2025 28 Apr 2025 14d 100% 2,140
05.02 NWF-0520 Inter-Array Cable Lay — Strings 3–6 (T17–T48) 02 May 2025 15 Jul 2025 56d 100% 8,560
05.03 NWF-0530 Cable Burial & Rock Placement — All Strings 10 Apr 2025 01 Sep 2025 Rolling 100% 4,200
WBS 05 — Cable Installation Subtotal (46 activities) € 36,240K All ✓
WBS 06 — Offshore Substation (OSS) Installation  38 activities
06.01 NWF-0601 OSS Jacket Fabrication Complete 01 Jun 2024 30 Nov 2024 130d 100% 8,400
06.02 NWF-0610 OSS Jacket Installation — Marine Heavy Lift 15 Jan 2025 25 Jan 2025 10d 100% 3,200
06.03 NWF-0620 OSS Topside Set & Grouting 01 Mar 2025 20 Mar 2025 18d 100% 4,600
06.04 NWF-0630 HV Cable — OSS to Shore — Lay & Bury (48km) 01 Jun 2025 15 Sep 2025 77d 100% 18,400
WBS 06 — Offshore Substation Subtotal (38 activities) € 48,200K All ✓
WBS 07 — Pre-Commissioning & Commissioning  44 activities
07.01 NWF-0701 HV Cable Hi-Pot Test — Full Array 18 Sep 2025 30 Sep 2025 10d 100% 380
07.02 NWF-0710 First Energisation — OSS to Shore 05 Oct 2025 05 Oct 2025 1d 100%
07.03 NWF-0720 WTG Pre-Commissioning — All 48 Turbines 01 Oct 2025 20 Dec 2025 Rolling 100% 4,800
07.04 NWF-0730 Grid Connection Test & Energisation Certificate 22 Dec 2025 10 Jan 2026 14d 100% 680
07.05 NWF-0740 First Power Production — T01 to T48 14 Jan 2026 28 Jan 2026 14d 100%
WBS 07 — Commissioning Subtotal (44 activities) € 8,640K All ✓
WBS 08 — Demobilisation & Project Closeout  22 activities
08.01 NWF-0801 Vessel Demobilisation — Svanen III, Bold Tern, Nexans Aurora 28 Jan 2026 08 Feb 2026 10d 100% 2,400
08.02 NWF-0810 Document Handover — O&M Manuals, As-Built Drawings 28 Jan 2026 15 Feb 2026 14d 100% 180
08.03 NWF-0820 Final Punchlist Clearance & Handover Certificate 30 Jan 2026 15 Feb 2026 14d 100%
WBS 08 — Closeout Subtotal (22 activities) € 5,040K All ✓
TOTAL PROJECT — 312 Activities — All 100% Complete € 312,400K ✓ All
As-Built Schedule Verification Statement

This As-Built Schedule Report constitutes the official project record for the Nordic Wind Farm Phase 2 Offshore Array. All 312 activities are 100% complete. Actual start and actual finish dates have been verified against:

  • Daily Construction Reports (DCRs) — 1,024 reports covering the full project duration
  • Marine Installation Records (MIRs) — Verified by third-party marine warranty surveyor (Aqualis)
  • Vendor/Subcontractor Monthly Reports — Cross-checked for all 8 major subcontract packages
  • SCADA First Power Production logs — Confirming turbine energisation dates to the nearest hour
  • Final Account and Cost Ledger — Reconciled to €312,400,000 actual project cost

Approved by: E. Bergstrom (Senior Project Manager) — 15 Feb 2026. This document should be retained for a minimum of 25 years per the O&M Agreement and the relevant national maritime archive requirements.