R-32: Data Quality & Completeness Report
Data Date: 28 Feb 2026
Data Quality & Completeness Report
Pacific Rail Corridor Upgrade — PMO Data Quality Audit — 28 February 2026 Submission
ProjectPacific Rail Corridor Upgrade
ContractorTransRail Construction Joint Venture
Total Activities2,847
Data Date28 Feb 2026
Audit ReferenceDQ-2026-03
Overall Quality Score
71%
Grade: C+ (target ≥85%)
Required Fields at 100%
4 of 9
5 required fields below 100%
Activities Missing ≥1 Code
340
12.0% of all activities
Duplicate Activity Names
47
Pairs identified
Naming Violations
128
Non-conformant to NCS standard
Overall Quality Score Breakdown
71%
Data Quality
Grade C+
Target: 85%
Score Component Breakdown
Required Fields
78% Weight: 35%
Activity Codes
68% Weight: 25%
UDF Completeness
62% Weight: 15%
Naming Convention
95% Weight: 15%
Duplicate Check
98% Weight: 10%
Field Completeness Matrix
Category Field / UDF / Code Total Populated Empty % Complete Status PMO Mandate
Required Fields — Must be 100% populated per Contract Schedule Management Plan Clause 5.1
Required Activity ID 2,847 2,847 0 100.0% Compliant Mandatory
Required Activity Name 2,847 2,847 0 100.0% Compliant Mandatory
Required WBS Assignment 2,847 2,847 0 100.0% Compliant Mandatory
Required Original Duration 2,847 2,847 0 100.0% Compliant Mandatory
Required Responsible Party Code 2,847 2,418 429 84.9% Non-Compliant Mandatory
Required Discipline Code 2,847 2,507 340 88.1% Non-Compliant Mandatory
Required Work Area Code 2,847 2,591 256 91.0% Non-Compliant Mandatory
Required Phase / Stage Code 2,847 2,678 169 94.1% Warning Mandatory
Required Resource Assignment 2,847 2,703 144 94.9% Warning Mandatory
Recommended UDF Fields — Target 90%+ populated per PMO Schedule Data Requirements
UDF UDF: Planned Crew Size 2,847 2,204 643 77.4% Below Target Recommended
UDF UDF: Sub-Contractor Name 2,847 2,018 829 70.9% Below Target Recommended
UDF UDF: Scope of Work Reference 2,847 1,768 1,079 62.1% Below Target Recommended
UDF UDF: Risk Register Link 2,847 1,412 1,435 49.6% Below Target Recommended
UDF UDF: IFC Drawing Reference 2,847 2,391 456 84.0% Below Target Recommended
UDF UDF: Permit Required (Y/N) 2,847 2,712 135 95.3% Compliant Recommended
Activity Code Fields — Required for Cost Account and WBS Reporting Integration
Code Cost Account Code (CAC) 2,847 2,641 206 92.8% Warning Mandatory
Code Milestone Type Code 412 412 0 100.0% Compliant Optional
Code Inspection Hold Point Flag 2,847 2,180 667 76.6% Below Target Recommended
Code Priority Code (H/M/L) 2,847 1,924 923 67.6% Below Target Recommended
Duplicate Activity Name Check

47 duplicate activity name pairs were identified. Duplicate names create confusion in reports and can mask data entry errors. The Naming Convention Standard (NCS-2024) requires globally unique names across the project schedule.

Activity ID 1 Activity ID 2 Duplicate Name WBS 1 WBS 2
RC-1041 RC-2204 Install Sleeper Fastenings 02.01 04.02
RC-1810 RC-3301 Signal Cable Pulling 05.03 07.01
RC-2044 RC-2810 Ballast Tamping — Zone B 02.02 02.04
... 44 additional duplicate pairs (full list in Appendix DQ-1) ...
Naming Convention Violations (NCS-2024 Standard)
Violation Type Rule Violated Count Example Activity Name Action Required
Format NCS-R-01: Name must begin with verb (Mobilise/Install/Test/Inspect) 54 Track Gangs - Zone 4 (missing verb) Rename
Format NCS-R-02: Name must include location reference in brackets [Zone X / Area Y] 38 Lay Rail Track (no location) Rename
Length NCS-R-03: Maximum 80 characters 17 Install Overhead Line Equipment including stanchions, registration arms, and droppers at all attachment points [Sector 3 North bound line between km 142.3 and km 148.7] Truncate
Format NCS-R-04: No special characters except hyphen, brackets, forward slash 12 Test & Commission Signal Box #4 (use of # and &) Rename
Convention NCS-R-05: Milestone names must end in "— Complete" or "— Approved" 7 Piling Done (should end in — Complete) Rename
Contractor Remediation Plan — Required Actions by 28 Mar 2026
Priority Issue Count Deadline Owner Status
P1 — Critical Populate Responsible Party Code for all 429 activities 429 14 Mar 2026 Scheduler In Progress
P1 — Critical Assign Discipline Code to 340 uncoded activities 340 14 Mar 2026 Scheduler In Progress
P1 — Critical Assign Work Area Code to 256 activities 256 14 Mar 2026 Scheduler In Progress
P2 — High Resolve 47 duplicate activity name pairs per NCS-2024 47 21 Mar 2026 Lead Scheduler Not Started
P2 — High Correct 128 naming convention violations 128 21 Mar 2026 Lead Scheduler Not Started
P3 — Medium Populate UDF: Sub-Contractor Name (currently 70.9%) 829 28 Mar 2026 Package Managers Not Started
P3 — Medium Populate UDF: Scope of Work Reference (currently 62.1%) 1,079 28 Mar 2026 Engineering Not Started
P4 — Low Populate UDF: Risk Register Link (currently 49.6%) 1,435 30 Apr 2026 Risk Manager Not Started
Data Quality Assessment Summary — 28 February 2026
  • PMO mandate status: The schedule currently scores 71% against the PMO Data Quality target of 85%. At this submission, 5 of 9 required fields are below 100% — non-compliance with Schedule Management Plan Clause 5.1. The contractor has acknowledged the deficiencies and a remediation plan was submitted on 01 Mar 2026.
  • Critical gap — Activity Codes: 340 activities are missing at least one required code. These activities account for 62% of all PMO reporting failures this period, as cross-WBS and discipline-level reports cannot be generated reliably for uncoded activities. The issue is concentrated in newly added activities from Change Directive CD-2025-44 (Track Upgrade Extension to Km 156).
  • UDF shortfall is the largest single contributor to the below-target score. The Scope of Work Reference (62.1%) and Risk Register Link (49.6%) fields are significantly below target. The PM has committed to completing these fields as part of the next monthly update cycle.
  • Positive indicators: Activity naming conventions are 95.3% compliant — a marked improvement from 82% at the previous audit. Permit Required flags are 95.3% populated. Milestones are 100% coded.
  • Resubmission: A re-audit will be conducted on 28 Mar 2026. The contractor must achieve ≥85% overall quality score or the monthly payment certificate will be held pending compliance per Contract Clause 14.3(b).