R-31: Baseline Variance Report
Data Date: 28 Feb 2026
Baseline Variance Report
Greenfields LNG Processing Facility — Schedule vs. Original Baseline (Rev 0) — Data Date: 28 February 2026
ProjectGreenfields LNG Processing Facility
Total Activities3,042
Baseline RevRev 0 — 01 Mar 2025
Data Date28 Feb 2026
Project Completion+47d vs. Baseline
Avg Finish Variance
+14.3d
All active activities
Activities >10d Late
502
16.5% of schedule
Activities >20d Late
218
7.2% of schedule
Critical Path Variance
30 on CP
of 502 activities >10d slip
On / Ahead of BL
1,641
53.9% at or ahead of BL
Variance Distribution Histogram
Start Variance Distribution (BL Start vs Forecast Start)
42
<−20d
187
−20 to −10
524
−10 to 0
871
0 to +10
298
+10 to +20
120
+20 to +30
>+30d
Negative = ahead of baseline start. Positive = delayed vs. baseline start. Values in working days.
Finish Variance Distribution (BL Finish vs Forecast Finish)
28
<−20d
143
−20 to −10
671
−10 to 0
799
0 to +10
284
+10 to +20
176
+20 to +30
42
>+30d
Negative = finishing early vs. baseline. Positive = delayed vs. baseline finish. Values in working days.
Threshold Exceedance Summary
502
Variance > 10 Days
16.5% of 3,042 activities
30 on Critical Path
218
Variance > 20 Days
7.2% of 3,042 activities
12 on Critical Path
76
Variance > 30 Days
2.5% of 3,042 activities
8 on Critical Path
1,641
At / Ahead of Baseline
53.9% on or early
Majority on track
Top 20 Activities by Absolute Finish Variance
# Activity ID Activity Name WBS BL Finish Fcst Finish Variance CP? Status
1 LNG-3042 Cold Box Module Fabrication — Train 2 03.02 15 Jan 2026 27 Apr 2026 +71d CP In Progress
2 LNG-2814 Mechanical Equipment Delivery — Compressor A 03.01 20 Nov 2025 10 Mar 2026 +63d CP Not Started
3 LNG-3105 Piping Spools — Cryogenic Service, Area 3 04.03 05 Feb 2026 15 Apr 2026 +55d CP In Progress
4 LNG-1922 Foundation Piling — Storage Tank 4 02.04 10 Oct 2025 30 Jan 2026 +52d Near-CP Complete
5 LNG-4201 High Voltage Switchgear Installation 06.01 30 Jan 2026 10 Apr 2026 +50d CP Not Started
6 LNG-2330 Instrument Air Package Commissioning 07.02 15 Dec 2025 15 Mar 2026 +45d Off-CP Not Started
7 LNG-1750 Pre-Commissioning — Relief Valve Headers 07.04 22 Nov 2025 30 Jan 2026 +43d Off-CP Complete
8 LNG-3601 Structural Steelwork — Flare Boom Tower 02.06 01 Feb 2026 10 Mar 2026 +31d Off-CP In Progress
9 LNG-2044 Electrical Cable Tray — Zone B Upper Level 06.02 10 Jan 2026 12 Feb 2026 +29d Off-CP Complete
10 LNG-4082 Insulation — Cryogenic Piping, Area 4 05.04 28 Jan 2026 20 Mar 2026 +28d Off-CP In Progress
11 LNG-2751 HVAC Ductwork — Control Room Building 05.01 15 Jan 2026 05 Mar 2026 +27d Off-CP In Progress
12 LNG-3320 Vessel Nozzle Orientation Checks — V-205 03.03 20 Dec 2025 10 Feb 2026 +27d Off-CP Complete
13 LNG-1310 Concrete Topping Slab — Pipe Rack Bays 5–8 02.01 30 Nov 2025 20 Jan 2026 +26d Off-CP Complete
14 LNG-4450 Fire & Gas Detection — Train 1 Integration Test 08.01 15 Feb 2026 10 Mar 2026 +22d Off-CP Not Started
15 LNG-2900 Offshore Berthing Arm Installation — Jetty 1 09.01 05 Feb 2026 25 Feb 2026 +20d Off-CP In Progress
... Activities 16–20 omitted for brevity (variances range +15 to +19 days) ...
Red highlight = Critical Path activity. Amber highlight = Near-Critical Path (TF ≤ 5d). CP variance drives project end-date slippage.
WBS-Level Finish Variance Summary
WBS WBS Description Activities Avg Var (d) Max Var (d) >10d >20d Trend
01 Civil & Earthworks 312 +8.4 +52 42 18 Stable
02 Structural & Concrete 287 +3.1 +31 18 4 Improving
03 Mechanical Equipment 198 +28.7 +71 134 89 Deteriorating
04 Piping 524 +12.2 +55 181 62 Stable
05 Insulation & Passive Fire Protection 210 +9.8 +28 44 12 Stable
06 Electrical 341 +21.4 +50 148 88 Deteriorating
07 Instrumentation & Controls 289 +7.6 +45 38 14 Improving
08 Pre-Commissioning & Commissioning 187 +11.3 +22 22 6 Stable
09 Jetty & Marine Works 112 +4.9 +20 12 3 Improving
10 Project Management & Closeout 82 +1.2 +8 0 0 On Track
Average Finish Variance Trend — Monthly (May 2025 to Feb 2026)
+2.1
May
+3.8
Jun
+5.9
Jul
+7.4
Aug
+9.1
Sep
+10.8
Oct
+12.0
Nov
+13.1
Dec
+13.8
Jan
+14.3
Feb
Average finish variance has grown +12 days over 10 months. Rate of growth is decelerating — from +2d/month in Q3 2025 to +0.5d/month in Feb 2026. Mechanical and Electrical WBS remain primary drivers.
Variance Assessment — Greenfields LNG Processing Facility
  • Project end-date impact is currently +47 working days driven by 8 critical path activities. Mechanical Equipment (WBS 03) and Electrical (WBS 06) are the primary delay sources. Cold Box Module fabrication delay (+71d) is the single largest CP contributor — delayed due to vendor capacity constraints at the fabricator's facility in Korea.
  • The majority of the 502 activities with >10d slip are off the critical path (472 of 502). These do not directly drive the end date but consume float. If float is fully consumed in Piping (WBS 04), the end-date impact could grow by a further 15–20 days.
  • Positive indicators: Structural/Concrete (WBS 02) and Jetty works (WBS 09) are improving. Rate of variance growth has decelerated to 0.5 days/month. Civil earthworks are substantially complete with managed risk.
  • Recovery actions required: (1) Cold Box Module — assess air-freight of components vs. sea freight to recover 10–15 days; (2) Electrical — mobilise additional cable pulling crew targeting 30 activities by 15 Mar 2026; (3) Issue a formal Recovery Schedule for CP activities by 07 Mar 2026.