Schedule Health Scorecard Report
PMO Portfolio View — 20 Contractor Schedules — February 2026 Data Cycle
Portfolio Average
71
Letter Grade: C+
Highest Score
94
Cascade Tunnel Rehab (A)
Lowest Score
44
Coastal Highway Pkg 7 (F)
Improved vs Jan
+4.2
pts avg; 14 of 20 improved
On Watchlist
4
Score < 60, escalated to PM
Composite Score Breakdown — Top Performer: Cascade Tunnel Rehabilitation
A
94/100
Health Score
Feb 2026
+3 vs Jan
Logic Completeness
18/20
Weight: 20%Contribution: +18.0
Float Distribution
16/20
Weight: 20%Contribution: +16.0
Baseline Fidelity
19/20
Weight: 20%Contribution: +19.0
Progress Consistency
18/20
Weight: 15%Contribution: +13.5
Resource Loading
12/15
Weight: 15%Contribution: +12.0
Constraint Usage
11/15
Weight: 10%Contribution: +7.3
Score Weighting Model
| Sub-Category |
What is Measured |
Weight |
Max Points |
Grade Bands |
| Logic Completeness |
Missing predecessors/successors, relationship types, lags/leads |
20% |
20 |
≥18 A 14–17 C <14 F |
| Float Distribution |
High float %, negative float count, float consumption rate |
20% |
20 |
≥16 A 12–15 C <12 F |
| Baseline Fidelity |
Activities added/deleted vs BL, logic changes, duration changes >10% |
20% |
20 |
≥17 A 13–16 C <13 F |
| Progress Consistency |
Out-of-sequence progress, % complete outliers, missed tasks |
15% |
20 |
≥16 A 12–15 C <12 F |
| Resource Loading |
% activities with resource assignments, histogram smoothness |
15% |
15 |
≥13 A 9–12 C <9 F |
| Constraint Usage |
Hard constraints %, constraint type distribution, justification rate |
10% |
15 |
≥12 A 8–11 C <8 F |
PMO Portfolio Ranking — February 2026 (20 Contractor Schedules)
| Rank |
Project / Schedule |
Score |
Grade |
vs Jan |
Logic |
Float |
BL Fidelity |
Progress |
Resources |
Status |
| 1 |
Cascade Tunnel Rehabilitation |
94 |
A |
+3 |
18 | 16 | 19 | 18 | 12 |
Excellent |
| 2 |
Metro Rail — Section 4B |
91 |
A |
+1 |
19 | 17 | 18 | 16 | 13 |
Excellent |
| 3 |
Riverfront Bridge Replacement |
88 |
B+ |
+5 |
17 | 15 | 18 | 15 | 14 |
Good |
| 4 |
Port Expansion — Phase 2 |
84 |
B |
+2 |
16 | 15 | 16 | 14 | 12 |
Good |
| 5 |
Airport Terminal Expansion |
81 |
B |
— |
15 | 14 | 17 | 13 | 11 |
Good |
| 6 |
Water Treatment Plant Upgrade |
79 |
C+ |
+6 |
15 | 13 | 16 | 13 | 10 |
Acceptable |
| 7 |
Highway Package — Sections 12–14 |
77 |
C+ |
+4 |
14 | 14 | 15 | 14 | 9 |
Acceptable |
| 8 |
Substation 4 & Grid Tie-In |
75 |
C |
+3 |
14 | 12 | 15 | 14 | 9 |
Acceptable |
| 9 |
Hospital Expansion — Block D |
72 |
C |
−1 |
13 | 12 | 15 | 13 | 8 |
Acceptable |
| 10 |
Stadium Precinct Works — Zone 3 |
70 |
C |
— |
13 | 11 | 15 | 13 | 8 |
Acceptable |
| 11 |
Reservoir Dam Remediation |
68 |
C |
+2 |
12 | 11 | 14 | 12 | 9 |
Acceptable |
| 12 |
Freight Rail Intermodal Terminal |
66 |
C− |
−2 |
12 | 10 | 13 | 12 | 9 |
Acceptable |
| 13 |
Gas Pipeline Replacement — Zone A |
64 |
C− |
−3 |
11 | 10 | 13 | 11 | 9 |
Acceptable |
| 14 |
Sewage Treatment — Secondary Works |
62 |
C− |
+1 |
11 | 10 | 12 | 11 | 8 |
Acceptable |
| 15 |
Coastal Highway — Package 4 |
60 |
D+ |
−4 |
10 | 9 | 12 | 10 | 8 |
Under Review |
| 16 |
Regional Bus Depot Expansion |
57 |
D |
−2 |
10 | 8 | 11 | 10 | 7 |
Watchlist |
| 17 |
Bridge Deck Renewal — Package 11 |
54 |
D |
−5 |
9 | 8 | 11 | 9 | 7 |
Watchlist |
| 18 |
Offshore Wind Cable Landing |
51 |
F |
−6 |
8 | 7 | 10 | 9 | 6 |
Escalated |
| 19 |
Distribution Centre — Stage 2 |
48 |
F |
−8 |
7 | 7 | 10 | 8 | 5 |
Escalated |
| 20 |
Coastal Highway — Package 7 |
44 |
F |
−9 |
7 | 6 | 9 | 7 | 4 |
Escalated |
Portfolio Score Trend — September 2025 to February 2026
Portfolio Average Score (100-point scale)
Common Failure Drivers
Resource Loading17/20
Hard Constraints14/20
Missing Logic12/20
High Float Areas10/20
Out-of-Seq Progress8/20
PMO Portfolio Assessment — February 2026
- Portfolio trajectory is positive — average score has improved from 59 to 71 over 6 months (+20%). However, 4 projects (Rank 17–20) are on the watchlist and require immediate contractor engagement.
- Coastal Highway Package 7 (Score: 44/F) has deteriorated 9 points in one month, driven by logic deletions and complete removal of resource assignments. This contractor has been issued a Schedule Compliance Notice and has 10 days to provide a remediation plan.
- Resource Loading remains the systemic failure point across 17 of 20 schedules. A PMO workshop is scheduled for 15 Mar 2026 to address resource loading best practices and provide template resource libraries to all contractors.
- Top 3 projects demonstrate that scores of 88–94 are achievable in this program. The PMO will facilitate peer knowledge transfer from Cascade Tunnel Rehabilitation team (Score 94) to the bottom quartile contractors.
- Target for May 2026 review: Portfolio average ≥75, no project below 55. Projects below 55 at May review will be subject to Schedule Oversight Intervention.