R-28: What-If Scenario Comparison Report
Data Date: 28 Feb 2026
What-If Scenario Comparison Report
Multi-Scenario Analysis: Sequential Build vs Fast-Track vs Design-Build — Northgate International Airport Expansion — Terminal 3
ProjectNorthgate Intl. Airport — Terminal 3 Expansion
Analysis Date28 Feb 2026
Scenarios Evaluated3
Decision Required By28 Mar 2026
AnalystP6 Controls Team
Earliest Possible Completion
Dec 2028
Scenario B — Fast-Track
Lowest Total Cost
$1.24B
Scenario A — Sequential
Lowest Risk Profile
Scenario A
Highest float, proven method
Recommended Scenario
B — Fast-Track
Best risk-adjusted outcome
CP Length Spread
24 mo
Between fastest and slowest
Scenario Summary — Side-by-Side KPI Comparison
Scenario A — Sequential Build
Traditional sequential phasing: Foundations → Structure → MEP → Fit-Out → Commissioning. Minimal concurrency, full design completion before each phase. Low rework risk.
End Date Dec 2029
Total Cost $1.24B
CP Length 47 months
Peak Headcount 620
P80 Schedule Risk +5.2 mo
Top Risk Design scope creep
Recommended
Feasible — Not Recommended
Scenario C — Design-Build (Single Contractor)
Single design-build contractor takes full design + construction responsibility. Maximum concurrency, fixed lump-sum price. Owner retains less design control. Contractor takes full scope risk.
End Date Jun 2028
Total Cost $1.68B
CP Length 23 months
Peak Headcount 1,450
P80 Schedule Risk +11.4 mo
Top Risk Contractor insolvency / QA
Recommended
High Risk — Not Recommended
Multi-Scenario Comparison Matrix
Parameter Scenario A — Sequential Scenario B — Fast-Track ✓ Scenario C — Design-Build Best
Project End Date Dec 2029 Dec 2028 Jun 2028 C (but high risk)
Total Project Cost (P50) $1.24B $1.41B $1.68B A
Cost Contingency (%) 5% 8% 15% A
Critical Path Length 47 months 35 months 23 months C (but very risky)
Peak Workforce 620 920 1,450 A
Average Total Float (non-CP) 38d 22d 8d A
P80 Completion Date May 2030 (+5.2 mo) Jul 2029 (+7.1 mo) May 2029 (+11.4 mo) B (risk-adj.)
Design Change Risk Low Medium High A
Rework / Abortive Work Risk Low Medium (8% allowance) High (15% allowance) A
Owner Design Control Full Full Reduced A/B
Supply Chain Complexity Standard Elevated High (single point) A
Contractor Insolvency Risk Low (multiple) Low (multiple) High (single) A/B
Airport Operational Disruption Moderate (4 yr) Lower (3 yr) Lowest (2 yr) C (but high risk)
Revenue Loss — Foregone $480M (47 mo) $360M (35 mo) $224M (23 mo) C (but high risk)
Overall Recommendation Feasible, not preferred RECOMMENDED Not Recommended Scenario B
Visual Metric Comparison (Normalized to Scenario A = 100%)
Total Cost
A — Sequential
$1.24B (base)
B — Fast-Track
$1.41B (+14%)
C — Design-Build
$1.68B (+35%)
CP Duration
A — Sequential
47 months
B — Fast-Track
35 months (−26%)
C — Design-Build
23 months (−51%)
Schedule Risk (P80)
A — Sequential
+5.2 mo (low)
B — Fast-Track
+7.1 mo (med)
C — Design-Build
+11.4 mo (high)
Peak Workforce
A — Sequential
620 persons
B — Fast-Track
920 persons
C — Design-Build
1,450 persons
Scenario Analysis Recommendation — Scenario B: Fast-Track Delivery

Scenario B (Fast-Track) is recommended as the optimal risk-adjusted delivery strategy for the Northgate Terminal 3 Expansion, based on the following analysis:

  • Time vs. Cost trade-off: The 12-month schedule advantage over Scenario A (Dec 2028 vs Dec 2029) yields $120M in additional airport revenue during the recovered operating period. The $170M cost premium for Scenario B is therefore net-positive by approximately $50M over a 10-year NPV model.
  • Scenario C rejected: While Design-Build offers 6 months' further time saving over Scenario B, the cost premium ($270M more than A) and concentrated contractor risk (single point of failure, 1,450 peak workforce) create unacceptable exposure. The P80 schedule risk of +11.4 months means Scenario C's headline completion date of Jun 2028 has only 20% probability of being achieved — effectively pushing the P50 outcome into 2029, eliminating the time advantage.
  • Risk mitigation for Scenario B: The key risks of rework from IFC design changes and mid-construction scope additions must be managed through a robust AFC freeze protocol and design freeze gates at each phase boundary. An 8% design contingency (included in the $1.41B estimate) is adequate to cover expected rework volumes based on comparable airport expansion projects.
  • Key decision milestone: Scenario B procurement strategy (multi-package traditional contracts) requires the appointment of a Design Manager by 01 May 2026 and completion of the Employer's Requirements document by 01 Jul 2026 to maintain the Dec 2028 target.
  • Decision required by 28 Mar 2026 to allow competitive tender issuance for foundations package on 15 May 2026 — the first critical milestone for the Scenario B schedule.