What-If Scenario Comparison Report
Multi-Scenario Analysis: Sequential Build vs Fast-Track vs Design-Build — Northgate International Airport Expansion — Terminal 3
Earliest Possible Completion
Dec 2028
Scenario B — Fast-Track
Lowest Total Cost
$1.24B
Scenario A — Sequential
Lowest Risk Profile
Scenario A
Highest float, proven method
Recommended Scenario
B — Fast-Track
Best risk-adjusted outcome
CP Length Spread
24 mo
Between fastest and slowest
Scenario Summary — Side-by-Side KPI Comparison
Scenario A — Sequential Build
Traditional sequential phasing: Foundations → Structure → MEP → Fit-Out → Commissioning. Minimal concurrency, full design completion before each phase. Low rework risk.
End Date
Dec 2029
Total Cost
$1.24B
CP Length
47 months
Peak Headcount
620
P80 Schedule Risk
+5.2 mo
Top Risk
Design scope creep
Recommended
✗
Feasible — Not Recommended
Recommended
Scenario B — Fast-Track
Overlapping design and construction phases. Foundation works commence on 30% design. Structural steel ordered on Design Development. Higher design contingency budgeted (8%).
End Date
Dec 2028
Total Cost
$1.41B
CP Length
35 months
Peak Headcount
920
P80 Schedule Risk
+7.1 mo
Top Risk
Rework from IFC changes
Recommended
✓
Best Risk-Adjusted Outcome
Scenario C — Design-Build (Single Contractor)
Single design-build contractor takes full design + construction responsibility. Maximum concurrency, fixed lump-sum price. Owner retains less design control. Contractor takes full scope risk.
End Date
Jun 2028
Total Cost
$1.68B
CP Length
23 months
Peak Headcount
1,450
P80 Schedule Risk
+11.4 mo
Top Risk
Contractor insolvency / QA
Recommended
✗
High Risk — Not Recommended
Multi-Scenario Comparison Matrix
| Parameter |
Scenario A — Sequential |
Scenario B — Fast-Track ✓ |
Scenario C — Design-Build |
Best |
| Project End Date |
Dec 2029 |
Dec 2028 |
Jun 2028 |
C (but high risk) |
| Total Project Cost (P50) |
$1.24B |
$1.41B |
$1.68B |
A |
| Cost Contingency (%) |
5% |
8% |
15% |
A |
| Critical Path Length |
47 months |
35 months |
23 months |
C (but very risky) |
| Peak Workforce |
620 |
920 |
1,450 |
A |
| Average Total Float (non-CP) |
38d |
22d |
8d |
A |
| P80 Completion Date |
May 2030 (+5.2 mo) |
Jul 2029 (+7.1 mo) |
May 2029 (+11.4 mo) |
B (risk-adj.) |
| Design Change Risk |
Low |
Medium |
High |
A |
| Rework / Abortive Work Risk |
Low |
Medium (8% allowance) |
High (15% allowance) |
A |
| Owner Design Control |
Full |
Full |
Reduced |
A/B |
| Supply Chain Complexity |
Standard |
Elevated |
High (single point) |
A |
| Contractor Insolvency Risk |
Low (multiple) |
Low (multiple) |
High (single) |
A/B |
| Airport Operational Disruption |
Moderate (4 yr) |
Lower (3 yr) |
Lowest (2 yr) |
C (but high risk) |
| Revenue Loss — Foregone |
$480M (47 mo) |
$360M (35 mo) |
$224M (23 mo) |
C (but high risk) |
| Overall Recommendation |
Feasible, not preferred |
RECOMMENDED |
Not Recommended |
Scenario B |
Visual Metric Comparison (Normalized to Scenario A = 100%)
Total Cost
A — Sequential
$1.24B (base)
B — Fast-Track
$1.41B (+14%)
C — Design-Build
$1.68B (+35%)
CP Duration
B — Fast-Track
35 months (−26%)
C — Design-Build
23 months (−51%)
Schedule Risk (P80)
A — Sequential
+5.2 mo (low)
B — Fast-Track
+7.1 mo (med)
C — Design-Build
+11.4 mo (high)
Peak Workforce
A — Sequential
620 persons
B — Fast-Track
920 persons
C — Design-Build
1,450 persons
Scenario Analysis Recommendation — Scenario B: Fast-Track Delivery
Scenario B (Fast-Track) is recommended as the optimal risk-adjusted delivery strategy for the Northgate Terminal 3 Expansion, based on the following analysis:
- Time vs. Cost trade-off: The 12-month schedule advantage over Scenario A (Dec 2028 vs Dec 2029) yields $120M in additional airport revenue during the recovered operating period. The $170M cost premium for Scenario B is therefore net-positive by approximately $50M over a 10-year NPV model.
- Scenario C rejected: While Design-Build offers 6 months' further time saving over Scenario B, the cost premium ($270M more than A) and concentrated contractor risk (single point of failure, 1,450 peak workforce) create unacceptable exposure. The P80 schedule risk of +11.4 months means Scenario C's headline completion date of Jun 2028 has only 20% probability of being achieved — effectively pushing the P50 outcome into 2029, eliminating the time advantage.
- Risk mitigation for Scenario B: The key risks of rework from IFC design changes and mid-construction scope additions must be managed through a robust AFC freeze protocol and design freeze gates at each phase boundary. An 8% design contingency (included in the $1.41B estimate) is adequate to cover expected rework volumes based on comparable airport expansion projects.
- Key decision milestone: Scenario B procurement strategy (multi-package traditional contracts) requires the appointment of a Design Manager by 01 May 2026 and completion of the Employer's Requirements document by 01 Jul 2026 to maintain the Dec 2028 target.
- Decision required by 28 Mar 2026 to allow competitive tender issuance for foundations package on 15 May 2026 — the first critical milestone for the Scenario B schedule.