Current vs Target Finish — Recovery Actions, Combined Impact Waterfall & Cost Summary — Westport Industrial Complex Package 3
ProjectWestport Industrial Complex — Package 3
Data Date28 Feb 2026
Recovery Plan Versionv1.2 — 28 Feb 2026
Approved Budget for Recovery$300,000
Current Forecast Finish (Leveled)
15 Jul 2027
Resource-leveled schedule — R-23 result
→
Contract Completion
31 Mar 2027
Original baseline — LD trigger
→
Recovery Required
−106d
to achieve contract
→
Target Finish (Post-Recovery)
27 May 2027
Net 48d recovered from 4 actions (−$247K)
→
Remaining Gap
57d
Above budget to close — EOT path or scope change
Current Delay vs Contract
+106d
Jul 2027 vs Mar 2027
Recovery Actions
4
identified & costed
Total Days Recovered
48d
net after interactions
Recovery Cost
$247K
of $300K budget
Remaining Gap
57d
requires EOT or scope
Recovery Actions Register
Action #
Recovery Action
Target Activity / Area
Days Recovered
Additional Cost
Resource Impact
Dependencies
Priority
Status
RA-01
Secure 30 Additional Electricians from Regional Sub-Contractors
E-2410 MV Switchgear Terminations
22
$85,000
+30 electricians, Aug–Oct 2026
Pre-qualification by 20 Mar 2026
P1 — Critical
In Progress
RA-02
Authorize 6-Day Working Week for Mechanical Crews
M-3100, M-3120 — Mechanical Installation
18
$62,000
+20% mech. crew cost, 12 wks
Board approval of OT budget
P1 — Critical
Pending Approval
RA-03
Fast-Track Concrete Zone B with Second Ready-Mix Supplier
C-0810 — Slab on Grade Process Area B
6
$48,000
3rd concrete gang, 8 wks
Batch plant approval (Environmental)
P2 — High
In Planning
RA-04
Logic Optimization — Overlap Piping Fabrication with Foundation Completion
P-1210, P-1840 — Piping Chain
14
$52,000
Spool shop crew 3 wks ahead
IFC drawings for P-1210 issued
P2 — High
Approved
TOTAL / NET (after interaction factor −12d)
48
$247,000
Combined interaction reduces raw 60d gain to 48d net
Recovery Waterfall — Delay vs Recovery by Action
Resource Impact of Recovery Plan
Electricians (Peak)
95 available→125 with RA-01
Closes shortage; resolves Sep over-cap
Mechanical Fitters (Peak)
75 @ 5d/wk→75 @ 6d/wk (RA-02)
18% effective capacity increase; no new headcount
Concrete Gangs
2 gangs→3 gangs (RA-03)
+50% concrete placement capacity Zone B
Pipefitters — Spool Fab.
Start: May 2026→Start: Feb 2026 (RA-04)
Spool shop team mobilized earlier; float consumed
Total Recovery Cost
$247,000
82% of $300K approved budget utilised
Recovery Cost Summary
Action
Cost Component
Amount
Cost Code
Days Recovered
Cost / Day Recovered
Value Assessment
RA-01
Electrical subcontractor premium + mobilization
$85,000
WIC-REC-001
22
$3,864
Excellent
RA-02
6-day week premium (20% OT rate, 75 staff, 12 wks)
$62,000
WIC-REC-002
18
$3,444
Excellent
RA-03
Third concrete gang hire + second RMC supply contract
$48,000
WIC-REC-003
6
$8,000
Moderate
RA-04
Early spool shop mobilization + IFC drawing expedite
$52,000
WIC-REC-004
14
$3,714
Excellent
TOTAL
All recovery actions
$247,000
48 (net)
$5,146
vs LD rate $20K/day
Recovery Schedule Recommendation
The proposed 4-action recovery plan costs $247,000 and recovers a net 48 calendar days — reducing the forecast delay from 106 days to 58 days. At an average recovery cost of $5,146/day against a Liquidated Damages rate of $20,000/day, all four actions deliver exceptional commercial value.
Remaining 58-day gap: The concurrent delay entitlement (R-26 analysis) of 20 days plus the 40-day accepted EOT brings contractor entitlement to 60 days. The remaining 58-day gap therefore falls within the contractor's EOT entitlement window — subject to formal claim resolution, no LDs should apply.
Risk to recovery plan: RA-01 depends on confirming 30 additional electricians by 20 Mar 2026. If only 20 are confirmed, net recovery reduces from 48d to 39d. Early pre-qualification outreach to three identified regional contractors is already in progress (Powerline Specialists Ltd, CW Electrical, Apex MEP).
Approved actions: RA-04 is approved and actioned. RA-01 and RA-02 pending board approval of supplementary OT and subcontract budget by 07 Mar 2026. RA-03 pending Environmental permit for additional batch plant location.
Recovery schedule v1.2 to be re-baselined in P6 by 21 Mar 2026 once RA-01 through RA-04 approvals are confirmed.