R-25: Schedule Risk Assessment Report
Data Date: 28 Feb 2026
Schedule Risk Assessment Report
Activity Risk Scoring Matrix — Float, Duration, Resource, Logic & Historical Risk Factors — Westport Industrial Complex
ProjectWestport Industrial Complex — Package 3
Data Date28 Feb 2026
Activities Assessed184
High Risk Activities10
Risk Score MethodWeighted 5-Factor (P6 Risk)
High Risk Activities
10
score ≥ 4.0 / 5.0
Medium Risk
34
score 2.5–3.9
Low Risk
140
score < 2.5
Avg. Composite Score
2.3
all activities
Top Risk Activity
4.7
E-2410 (Elec.)
Risk Score Distribution Heatmap (Probability vs. Impact)
Schedule Impact →
Minimal
Minor
Moderate
Significant
Severe
Very High
2
1
3
4
3
High
3
5
4
2
1
Medium
8
6
5
3
1
Low
22
18
11
4
2
Very Low
45
20
10
3
1
↑ Likelihood
Risk Category Summary
High Risk (score ≥ 4.0)
10
Medium Risk (2.5–3.9)
34
Low Risk (≤ 2.4)
140
Scoring Factors (weighted):
Float (25%), Duration (20%), Resource (25%), Predecessors (15%), Historical (15%)
Top 10 Highest Risk Activities — Detail Register
Rank Activity ID Activity Name Float Float Sc. Dur. Sc. Res. Sc. Pred. Sc. Hist. Sc. Composite Risk Mitigation Owner
1 E-2410 MV Switchgear Terminations 15d 2.5 5.0 5.0 4.0 5.0 4.7 High Secure 30 add. electricians; overtime plan J. Martinez
2 M-3100 Major Equip. Setting — Package 4 8d 4.0 3.5 5.0 5.0 4.0 4.4 High Confirm crane availability; pre-rig plan R. Okonkwo
3 P-1840 Utility Header — Final Tie-Ins 3d 5.0 3.0 4.0 5.0 3.5 4.2 High Increase pipefitter allocation; 6-day week A. Torres
4 STR-2050 Secondary Steel — Zone 3 (sole supplier) 4d 4.5 3.0 4.0 3.5 3.0 4.0 High Qualify alternate steel fabricator by Mar 26 B. Singh
5 CV-0520 Piled Foundation — Zone C (soil conditions) 15d 2.5 4.0 3.0 3.5 5.0 4.0 High Add geotechnical contingency; pre-probe Zone C D. Osei
6 E-2430 Instrument Loop Testing 0d 5.0 3.5 3.5 4.0 3.0 3.9 Medium-H Resolve E-2410 first; specialist vendor on call J. Martinez
7 M-3120 Process Piping Hydrotest — Systems 1–4 0d 5.0 3.5 3.0 4.0 3.5 3.8 Medium-H Pressure test equipment pre-mobilised on site A. Torres
8 PROC-0810 DCS Cabinet Delivery & Installation 12d 3.0 3.5 3.5 3.5 4.5 3.6 Medium-H Track vendor; long-lead expediting weekly F. Nguyen
9 C-0810 Slab on Grade — Process Area B (productivity) 22d 2.0 3.5 3.0 3.5 5.0 3.4 Medium-H Second supplier; third concrete gang P. Brandt
10 STR-1040 Foundation Design Review — Sr. Eng. Conflict 0d 5.0 2.5 4.5 2.5 2.5 3.3 Medium-H Resolve Whitfield overallocation (R-22 action) J. Whitfield
Risk Spotlight — Activity E-2410: MV Switchgear Terminations (Score 4.7 / 5.0)

Despite a 15-day total float buffer, E-2410 scores as the highest-risk activity in the project due to the compound effect of all five risk factors. The "healthy float" is deceptive because:

  • Resource risk (5.0/5.0): Single specialized resource — licensed MV electricians — required at 120 persons peak. Only 95 confirmed available regionally. The 25-person shortage has no contingent source identified.
  • Duration risk (5.0/5.0): 89-day duration activity with 100% productivity dependency on electrician availability. Any daily crew shortfall compounds over the full duration.
  • Historical risk (5.0/5.0): MV switchgear termination activities on comparable projects have historically run 20–35% longer than estimated (4 data points in corporate project database). Baseline rate not adjusted for congested tray environment in Westport.
  • Paradox of healthy float: The 15d float is consumed entirely by the Sep 2026 overload scenario (R-23 analysis). Effective float is 0 days — the activity is operationally critical.