R-23: Leveling Impact Report
Data Date: 28 Feb 2026
Leveling Impact Report
Before / After Schedule Comparison Following Resource Leveling Run — Westport Industrial Complex Package 3
ProjectWestport Industrial Complex — Package 3
Data Date28 Feb 2026
Leveling Run27 Feb 2026 — v4.1
Leveling MethodLate Start, Priority-Weighted
Pre-Leveling Project Finish
31 Mar 2027
Original schedule baseline
Post-Leveling Project Finish
15 Jul 2027
After resource leveling
Total Project Delay
+106 Days
Liquidated damages risk: $2.12M
Activities Delayed
23
of 184 total activities
Root Cause Resources
3
driving the 106d delay
Max Single Activity Delay
62d
Activity E-2410
Key Activities Identified
8
primary delay chain
Avg Delay (delayed acts.)
22d
median: 18 days
Unaffected Activities
161
87% of schedule intact
Before / After Activity Comparison — Key Activities
Activity ID Activity Name Pre-Level Finish Post-Level Finish Delay (d) Delay Bar Cause Resource Float Before Float After Impact
E-2410 MV Switchgear Terminations 15 Aug 2026 16 Oct 2026 62
Electricians (–25 peak) 0d CP 0d CP Drives End Date
E-2430 Instrument Loop Testing 05 Sep 2026 07 Nov 2026 63
Electricians (successor) 0d CP 0d CP Drives End Date
M-3100 Mechanical Equipment Setting 20 Jun 2026 21 Aug 2026 62
Mech. Fitters (–5 peak) 0d CP 0d CP Drives End Date
M-3120 Process Piping Hydrotest 15 Jul 2026 16 Sep 2026 63
Mech. Fitters (successor) 0d CP 0d CP Drives End Date
STR-2050 Secondary Steel Erection — Zone 3 10 May 2026 07 Jun 2026 28
Structural Steelworkers 32d 4d Near-Critical
P-1840 Utility Piping — North Header 30 Apr 2026 25 May 2026 25
Pipefitters 28d 3d Near-Critical
C-0910 Equipment Pads — Battery Limit 15 Mar 2026 30 Mar 2026 15
Concrete Crews 40d 25d Acceptable
E-1205 Underground Conduit — Zone 1 28 Mar 2026 11 Apr 2026 14
Electricians 35d 21d Acceptable
Delay Distribution — All Delayed Activities (23 Total)
8
1–10d
5
11–20d
4
21–30d
3
31–45d
3
46–65d
Delay bin distribution across 23 leveling-impacted activities. 6 activities exceed 20d delay — action required.
Delay by Root Cause Resource
Electricians (shortage 25) 10 activities
Mechanical Fitters (shortage 5) 8 activities
Structural Steelworkers (minor) 5 activities
Leveling Impact Assessment

The resource leveling run (v4.1, 27 Feb 2026) reveals a 106-calendar-day project end date slip driven almost entirely by the electrician shortage (25 persons below peak demand). The delay propagates through the electrical rough-in chain (E-2410 → E-2430 → Pre-Commissioning → Mechanical Completion) which sits on the critical path.

  • Acceptable impact: 13 activities delayed 1–20 days against float > 20d — no action needed. These are primarily civil and concrete activities in non-critical zones.
  • Recovery priority: Resolving the 25-person electrician shortfall (R-21 action) eliminates the E-2410 delay chain and recovers approximately 62 days — reducing net end date slip from 106d to 44d.
  • Remaining 44d gap: Primarily driven by mechanical fitter shortage (5 persons). Overtime authorization for M-3100 series (10% premium cost, est. $42K) can recover 20–25 days. The remaining 20–24 days can be addressed through scope/logic optimization (R-27 recovery schedule).
  • Leveling run must be re-executed after resource augmentation is confirmed — target: v4.2 by 14 Mar 2026.