Leveling Impact Report
Before / After Schedule Comparison Following Resource Leveling Run — Westport Industrial Complex Package 3
Pre-Leveling Project Finish
31 Mar 2027
Original schedule baseline
Post-Leveling Project Finish
15 Jul 2027
After resource leveling
Total Project Delay
+106 Days
Liquidated damages risk: $2.12M
Activities Delayed
23
of 184 total activities
Root Cause Resources
3
driving the 106d delay
Max Single Activity Delay
62d
Activity E-2410
Key Activities Identified
8
primary delay chain
Avg Delay (delayed acts.)
22d
median: 18 days
Unaffected Activities
161
87% of schedule intact
Before / After Activity Comparison — Key Activities
| Activity ID |
Activity Name |
Pre-Level Finish |
Post-Level Finish |
Delay (d) |
Delay Bar |
Cause Resource |
Float Before |
Float After |
Impact |
| E-2410 |
MV Switchgear Terminations |
15 Aug 2026 |
16 Oct 2026 |
62 |
|
Electricians (–25 peak) |
0d CP |
0d CP |
Drives End Date |
| E-2430 |
Instrument Loop Testing |
05 Sep 2026 |
07 Nov 2026 |
63 |
|
Electricians (successor) |
0d CP |
0d CP |
Drives End Date |
| M-3100 |
Mechanical Equipment Setting |
20 Jun 2026 |
21 Aug 2026 |
62 |
|
Mech. Fitters (–5 peak) |
0d CP |
0d CP |
Drives End Date |
| M-3120 |
Process Piping Hydrotest |
15 Jul 2026 |
16 Sep 2026 |
63 |
|
Mech. Fitters (successor) |
0d CP |
0d CP |
Drives End Date |
| STR-2050 |
Secondary Steel Erection — Zone 3 |
10 May 2026 |
07 Jun 2026 |
28 |
|
Structural Steelworkers |
32d |
4d |
Near-Critical |
| P-1840 |
Utility Piping — North Header |
30 Apr 2026 |
25 May 2026 |
25 |
|
Pipefitters |
28d |
3d |
Near-Critical |
| C-0910 |
Equipment Pads — Battery Limit |
15 Mar 2026 |
30 Mar 2026 |
15 |
|
Concrete Crews |
40d |
25d |
Acceptable |
| E-1205 |
Underground Conduit — Zone 1 |
28 Mar 2026 |
11 Apr 2026 |
14 |
|
Electricians |
35d |
21d |
Acceptable |
Delay Distribution — All Delayed Activities (23 Total)
Delay bin distribution across 23 leveling-impacted activities. 6 activities exceed 20d delay — action required.
Delay by Root Cause Resource
Electricians (shortage 25)
10 activities
Mechanical Fitters (shortage 5)
8 activities
Structural Steelworkers (minor)
5 activities
Leveling Impact Assessment
The resource leveling run (v4.1, 27 Feb 2026) reveals a 106-calendar-day project end date slip driven almost entirely by the electrician shortage (25 persons below peak demand). The delay propagates through the electrical rough-in chain (E-2410 → E-2430 → Pre-Commissioning → Mechanical Completion) which sits on the critical path.
- Acceptable impact: 13 activities delayed 1–20 days against float > 20d — no action needed. These are primarily civil and concrete activities in non-critical zones.
- Recovery priority: Resolving the 25-person electrician shortfall (R-21 action) eliminates the E-2410 delay chain and recovers approximately 62 days — reducing net end date slip from 106d to 44d.
- Remaining 44d gap: Primarily driven by mechanical fitter shortage (5 persons). Overtime authorization for M-3100 series (10% premium cost, est. $42K) can recover 20–25 days. The remaining 20–24 days can be addressed through scope/logic optimization (R-27 recovery schedule).
- Leveling run must be re-executed after resource augmentation is confirmed — target: v4.2 by 14 Mar 2026.