R-21: Resource Loading Report
Data Date: 28 Feb 2026
Resource Loading Report
Workforce Histogram by Role / Trade — Mobilization Through Demobilization — Westport Industrial Complex
ProjectWestport Industrial Complex — Package 3
Data Date28 Feb 2026
Contract Completion31 Mar 2027
Total Workforce~500 persons peak
Trades on Site6
Peak Headcount
498
Aug 2026
Capacity Ceiling
500
site constraint
Over-Cap Months
1
Sep 2026 (+14)
Mobilization Start
Mar 2026
ramp over 5 mo
Demob Complete
Mar 2027
12 mo ramp-down
Peak Demand Alert
120 Electricians — Aug 2026
Electrical rough-in, instrument cable tray, and MV switchgear terminations overlap in Aug 2026. Available electricians in region: 95. Recommend subcontractor pre-qualification by Mar 2026 to secure additional 30 resource headroom.
Monthly Resource Histogram — All Trades (Mar 2026 – Mar 2027)
500 375 250 125 0 Mar Apr May Jun Cap 500 500 400 300 200 100 0 Mar 26 Apr 26 May 26 Jun 26 Jul 26 Aug 26 498 Sep 26 514 ! Oct 26 Nov 26 Dec 26 Jan 27 Feb 27 Mar 27 CAP ↑ Mobilization Ramp ↓ Demobilization
Civil Works
Concrete / Formwork
Structural Steel
Mechanical
Piping
Electrical
Site Capacity (500)
* Sep 2026 exceeds site capacity by 14 persons (514 vs 500). Highlighted column requires leveling action.
Role Loading Summary — Peak Month Analysis
Role / Trade Mobilization Peak Month Peak Demand Available Over / (Under) Demobilization Risk
Electricians May 2026 Aug 2026 120 95 +25 Jan 2027 High
Mechanical Fitters May 2026 Oct 2026 80 75 +5 Dec 2026 Med
Pipefitters / Welders Jun 2026 Oct 2026 75 80 −5 Dec 2026 Low
Structural Steelworkers Apr 2026 Jul 2026 70 70 0 Nov 2026 Low
Concrete / Formwork Mar 2026 Jun 2026 70 85 −15 Oct 2026 Low
Civil / Earthworks Mar 2026 May 2026 60 65 −5 Sep 2026 Low
TOTAL — Peak Month (Sep 2026) Sep 2026 514 500 +14 Action Req.
Controls Analysis — Resource Loading

The workforce profile shows a classic single-peak construction curve with peak headcount of 498 in Aug 2026 and site capacity breach of 14 persons in Sep 2026. Two immediate actions are required:

  • Pre-qualify regional electrical subcontractors by Mar 2026 to secure 30 additional electricians for the Aug–Oct window. Electrical Rough-In (E-2410 series) drives the critical path and cannot be delayed.
  • Reschedule Mechanical Equipment Setting (M-3100) two weeks earlier to Sep 2026 to absorb part of the Mechanical peak demand, reducing Sep overload from +14 to approximately +5.
  • Civil demobilization (Aug 2026) frees approximately 25 welfare and welfare accommodation spaces to accommodate electrical peak — no additional camp expansion required.