Workforce Histogram by Role / Trade — Mobilization Through Demobilization — Westport Industrial Complex
ProjectWestport Industrial Complex — Package 3
Data Date28 Feb 2026
Contract Completion31 Mar 2027
Total Workforce~500 persons peak
Trades on Site6
Peak Headcount
498
Aug 2026
Capacity Ceiling
500
site constraint
Over-Cap Months
1
Sep 2026 (+14)
Mobilization Start
Mar 2026
ramp over 5 mo
Demob Complete
Mar 2027
12 mo ramp-down
Peak Demand Alert
120 Electricians — Aug 2026
Electrical rough-in, instrument cable tray, and MV switchgear terminations overlap in Aug 2026. Available electricians in region: 95.
Recommend subcontractor pre-qualification by Mar 2026 to secure additional 30 resource headroom.
Monthly Resource Histogram — All Trades (Mar 2026 – Mar 2027)
Civil Works
Concrete / Formwork
Structural Steel
Mechanical
Piping
Electrical
Site Capacity (500)
* Sep 2026 exceeds site capacity by 14 persons (514 vs 500). Highlighted column requires leveling action.
Role Loading Summary — Peak Month Analysis
Role / Trade
Mobilization
Peak Month
Peak Demand
Available
Over / (Under)
Demobilization
Risk
Electricians
May 2026
Aug 2026
120
95
+25
Jan 2027
High
Mechanical Fitters
May 2026
Oct 2026
80
75
+5
Dec 2026
Med
Pipefitters / Welders
Jun 2026
Oct 2026
75
80
−5
Dec 2026
Low
Structural Steelworkers
Apr 2026
Jul 2026
70
70
0
Nov 2026
Low
Concrete / Formwork
Mar 2026
Jun 2026
70
85
−15
Oct 2026
Low
Civil / Earthworks
Mar 2026
May 2026
60
65
−5
Sep 2026
Low
TOTAL — Peak Month (Sep 2026)
—
Sep 2026
514
500
+14
—
Action Req.
Controls Analysis — Resource Loading
The workforce profile shows a classic single-peak construction curve with peak headcount of 498 in Aug 2026 and site capacity breach of 14 persons in Sep 2026. Two immediate actions are required:
Pre-qualify regional electrical subcontractors by Mar 2026 to secure 30 additional electricians for the Aug–Oct window. Electrical Rough-In (E-2410 series) drives the critical path and cannot be delayed.
Reschedule Mechanical Equipment Setting (M-3100) two weeks earlier to Sep 2026 to absorb part of the Mechanical peak demand, reducing Sep overload from +14 to approximately +5.
Civil demobilization (Aug 2026) frees approximately 25 welfare and welfare accommodation spaces to accommodate electrical peak — no additional camp expansion required.