R-18: EAC Trending Report
Data Date: 28 Feb 2026
Estimate at Completion (EAC) Trending Report
8-Period EAC Method Comparison — Divergence Analysis
Project
Sunrise LNG Terminal
Contract Type
Lump Sum EPC
Data Date
28 Feb 2026
BAC
$485.0M
Current CPI
0.89
EAC Divergence
$43.7M range
BAC
$485.0M
Original Budget
EAC (CPI Method)
$544.9M
+$59.9M vs BAC (+12.4%)
EAC (SPI×CPI)
$588.6M
+$103.6M vs BAC (+21.4%)
EAC (Management)
$516.0M
+$31.0M vs BAC (+6.4%)
EAC (Bottom-Up)
$528.6M
+$43.6M vs BAC (+9.0%)
EAC Range
$43.7M
CPI vs Management spread
EAC Method Trend Lines — 8 Periods (Jul 2025 – Feb 2026)
EAC by Method — Period-over-Period Trend ($M)
CPI Method (BAC/CPI)
SPI×CPI Method
Management Estimate
Bottom-Up ETC
BAC = $485.0M
460 480 500 520 540 560 580 BAC Jul'25 Aug'25 Sep'25 Oct'25 Nov'25 Dec'25 Jan'26 Feb'26 $544.9M $588.6M $516.0M $528.6M
EAC Values by Period and Method ($M)
Method Jul'25 Aug'25 Sep'25 Oct'25 Nov'25 Dec'25 Jan'26 Feb'26 ◀ Δ 8-Period
BAC (Reference) 485.0 485.0 485.0 485.0 485.0 485.0 485.0 485.0
CPI Method BAC / CPI 488.9 494.1 499.2 508.5 519.0 531.3 539.0 544.9 +56.0
SPI×CPI Method ACWP + ETC/(SPI×CPI) 491.8 501.7 517.8 534.3 551.9 566.8 579.9 588.6 +96.8
Management Estimate ACWP + Risk-adj ETC 490.0 491.5 494.8 499.7 505.1 510.2 513.6 516.0 +26.0
Bottom-Up ETC ACWP + Detailed ETC 491.0 494.9 501.9 509.8 516.3 522.0 526.1 528.6 +37.6
Supporting EV Metrics — Period History
Metric Jul'25 Aug'25 Sep'25 Oct'25 Nov'25 Dec'25 Jan'26 Feb'26 ◀
CPI (cumulative) 0.992 0.982 0.972 0.953 0.934 0.914 0.900 0.890
SPI (cumulative) 0.995 0.984 0.970 0.951 0.937 0.921 0.910 0.906
BCWP CTD ($M) 48.2 89.6 134.1 179.8 220.0 256.3 288.4 310.6
ACWP CTD ($M) 48.6 91.2 137.9 188.6 235.5 280.3 320.4 349.0
CV CTD ($M) -0.4 -1.6 -3.8 -8.8 -15.5 -24.0 -32.0 -38.4
TCPI (to BAC) 1.001 1.004 1.009 1.019 1.030 1.043 1.053 1.061
EAC Divergence Alert — Management Estimate vs. CPI-Based Projection

The Sunrise LNG Terminal project shows an $28.9M divergence between the Management Estimate ($516.0M) and the CPI-based EAC ($544.9M) as of February 2026. This gap has widened steadily from $1.1M in July 2025 to $28.9M today, indicating that management estimates are increasingly optimistic relative to demonstrated cost performance.

The CPI has degraded monotonically from 0.992 to 0.890 over 8 periods with no month-over-month improvement, suggesting systemic cost growth rather than one-time events. TCPI to achieve the BAC now stands at 1.061 — requiring a 6.1% improvement in future cost efficiency, which is considered unlikely given the trend.

Recommended Action: Conduct formal Independent Cost Estimate (ICE) reconciliation between Management and CPI methods before the next Control Account Manager (CAM) review scheduled for 15 March 2026. If CPI continues below 0.90 next period, a formal Estimate to Complete (ETC) re-baseline should be initiated per contract CDRL A012.