Cost Variance by WBS Report
Sorted by Worst CV% — WBS Levels 1–4 with Drill Path
Total BAC
$218.4M
Budget at Completion
Total BCWP
$118.3M
Earned Value CTD
Total ACWP
$124.1M
Actual Cost CTD
Total CV
-$5.8M
Cost Variance
WBS Over Budget
3 of 8
WBS Level-2 nodes
WBS Under Budget
2 of 8
WBS Level-2 nodes
All WBS
›
Level 2 — Discipline
›
Level 3 — System
›
Level 4 — Activity
WBS Cost Variance Detail — Sorted by CV% (Worst First)
| WBS Code |
Name |
BAC ($K) |
BCWP ($K) |
ACWP ($K) |
CV ($K) |
CV % |
CPI |
Status |
Variance Bar |
| 1.4 |
Mechanical Systems |
38,200 |
20,700 |
23,800 |
-3,100 |
-15.0% |
0.87 |
Over Budget |
|
| 1.4.1 |
HVAC Distribution |
14,800 |
8,200 |
9,600 |
-1,400 |
-17.1% |
0.85 |
Over Budget |
|
| 1.4.1.1 |
OR Suite Ductwork |
6,100 |
3,200 |
3,950 |
-750 |
-23.4% |
0.81 |
Over Budget |
|
| 1.4.2 |
Plumbing & Medical Gas |
12,400 |
6,800 |
7,900 |
-1,100 |
-16.2% |
0.86 |
Over Budget |
|
| 1.4.3 |
Fire Protection |
11,000 |
5,700 |
6,300 |
-600 |
-10.5% |
0.90 |
Over Budget |
|
| 1.2 |
Structural |
44,600 |
31,200 |
33,400 |
-2,200 |
-7.1% |
0.93 |
Over Budget |
|
| 1.2.1 |
Concrete Structure |
32,000 |
22,400 |
24,200 |
-1,800 |
-8.0% |
0.93 |
Over Budget |
|
| 1.2.2 |
Steel & Connections |
12,600 |
8,800 |
9,200 |
-400 |
-4.5% |
0.96 |
At Risk |
|
| 1.1 |
Civil & Site Works |
18,900 |
15,600 |
16,100 |
-500 |
-3.2% |
0.97 |
At Risk |
|
| 1.3 |
Architecture & Interiors |
31,400 |
17,200 |
17,300 |
-100 |
-0.6% |
1.00 |
On Budget |
|
| 1.6 |
IT & Communications |
14,200 |
6,300 |
5,900 |
+400 |
+6.3% |
1.07 |
Under Budget |
|
| 1.5 |
Electrical Systems |
42,100 |
19,400 |
17,400 |
+2,000 |
+10.3% |
1.11 |
Under Budget |
|
| 1.5.1 |
HV Switchgear & Distribution |
16,800 |
8,100 |
7,100 |
+1,000 |
+12.3% |
1.14 |
Under Budget |
|
| 1.5.2 |
LV Wiring & Fit-out |
25,300 |
11,300 |
10,300 |
+1,000 |
+8.8% |
1.10 |
Under Budget |
|
| 1.7 |
Medical Equipment |
18,200 |
5,100 |
5,200 |
-100 |
-2.0% |
0.98 |
At Risk |
|
| 1.8 |
PM & Indirect |
10,800 |
3,000 |
4,000 |
-1,000 |
-33.3% |
0.75 |
Over Budget |
|
|
PROJECT TOTAL |
218,400 |
118,300 |
124,100 |
-5,800 |
-4.9% |
0.95 |
|
|
Cost Variance Treemap — WBS Level 2 (Area proportional to BAC, color = CV%)
1.2 Structural
BAC $44.6M · CV –7.1%
1.3 Architecture
BAC $31.4M · CV –0.6%
1.5 Electrical
BAC $42.1M · CV +10.3%
1.4 Mechanical
BAC $38.2M · CV –15.0%
1.1 Civil
BAC $18.9M · CV –3.2%
1.7 Med Equip
BAC $18.2M · CV –2.0%
1.6 IT
BAC $14.2M · CV +6.3%
CV –5% to +5% (On Budget)
CV –10% to –20% (Over Budget)