R-13: Out-of-Sequence Activities Report
Data Date: 28 Feb 2026
Out-of-Sequence Activities Report
Progress-Ahead-of-Predecessor Analysis — NEOM South Logistics Hub (Fast-Track Design-Build)
ProjectNEOM South Logistics Hub
Data Date28 Feb 2026
Contract TypeEPC Fast-Track D&B
OOS Activities27
Logic MethodRetained Logic
Total OOS
27
this update period
Intentional
11
design-build overlap
Unintentional
12
require investigation
Under Review
4
pending confirmation
Avg Float Impact
−8.4d
unintentional OOS only
Intentional OOS (Design-Build Overlap) — 11 Activities
Design/Construction overlaps7
Prefab concurrent with civil3
Procurement overlap1
Avg float impact+2.1d (beneficial)
Client approved8/11
Unintentional OOS — 12 Activities
Work executed before pred complete8
Subcontractor coordination failure3
Site instruction override1
Avg float impact−8.4d (adverse)
Rework risk identified5/12
Out-of-Sequence Activity Register
Act ID Activity Name Act % Pred ID Predecessor Name Pred % Rel Type OOS Type Float Δ (d) Logic Mode
STR.012Foundation Formwork Design 60% CIV.005Geotechnical Investigation 80% FS Intentional +3
P/O
STL.025Steel Frame Detailed Design 45% CIV.012Substructure Completion 50% FS Intentional +4
P/O
FAB.030Steel Column Prefabrication 35% STL.025Steel Frame Detailed Design 45% SS Intentional +2
P/O
MEP.015HVAC Design & Engineering 70% ARC.008Architectural Concept Freeze 85% FS Intentional +1
P/O
PAV.020Asphalt Wearing Course 25% PAV.010Asphalt Base Course 60% FS Under Review −5
R/L
ELE.035Lighting Fixture Installation 30% ELE.022Lighting Circuit Cabling 55% FS Under Review −7
R/L
FIN.010Internal Wall Plastering 40% STR.050Masonry Block Wall Construction 20% FS Unintentional −12
R/L
FIN.025Floor Tiling — Warehouse A 55% MEP.040Underfloor Services Routing 30% FS Unintentional −18
R/L
EXT.015External Hardstanding Concrete 20% CIV.090Underground Services Backfill 0% FS Unintentional −22
R/L
ARC.055Glazing Installation — Facade N 30% STR.065Structural Steel Facade Frame 15% FS Unintentional −9
R/L
COM.020BMS Panel Programming 15% ELE.080BMS Field Devices Wiring 5% SS Unintentional −6
R/L
PAV.035Line Marking — Yards 10% PAV.025Asphalt Seal Coat 0% FS Unintentional −3
R/L

R/L = Retained Logic (Primavera default — successor delayed until predecessor complete) · P/O = Progress Override (successor continues regardless). Float Δ = impact on activity TF under Retained Logic. Intentional OOS activities are approved design-build overlaps; unintentional require corrective action.

Unintentional OOS Risk

FIN.025 (Floor Tiling) proceeding before MEP.040 (Underfloor Services) creates immediate rework risk — 450 m² of tiling may require break-up to complete underground drainage connections. EXT.015 also at risk: hardstanding poured without backfill of services trench confirms site instruction not aligned with schedule. Potential EOT claim by MEP subcontractor.

Retained Logic Recommendation

Project is using Progress Override mode. Recommend switching to Retained Logic for the next update cycle to properly forecast completion dates for OOS activities. 12 unintentional OOS activities show −8.4d average float impact under Retained Logic — 3 activities would become critical. Owner notification may be required per contract clause 14.8.