R-12: Relationship & Logic Report
Data Date: 28 Feb 2026
Relationship & Logic Report
Relationship Register with Flag Analysis — Contractor Schedule Compression Detection · Al Noor Industrial Complex
ProjectAl Noor Industrial Complex
Data Date28 Feb 2026
Total Relationships1,842
Flagged218 (11.8%)
SS+Lag Count200
Total Rels
1,842
in current schedule
Non-FS Rels
463
25.1% of total
Flagged: Lag >5d
142
7.7% of total
Lag >50% Succ OD
76
schedule compression risk
Negative Lag (Lead)
38
artificial compression
Relationship Type Distribution
1,379
FS
74.9%
263
SS
14.3%
142
FF
7.7%
58
SF
3.1%
Flagged Relationship Register (Showing 20 of 218)
Pred ID Predecessor Name Succ ID Successor Name Type Lag (d) Lag % OD Justification Flags
CIV.050Foundation Slab Concrete STR.010Steel Frame Erection SS 4563% Curing time Lag >5d Lag >50% OD
STR.010Steel Frame Erection MEC.020Mechanical Equipment Install SS 3879% Access required Lag >5d Lag >50% OD
ELE.010HV Cable Pulls ELE.025Terminations & Testing SS -8−18% None on file Neg. Lag (Lead) Non-FS
CIV.080Drainage Pipes Installation PAV.010Asphalt Base Course FS 1444% Testing & backfill period Lag >5d
MEC.030Piping Fabrication MEC.045Hydrostatic Test FF 1028% Phased testing Lag >5d Non-FS
STR.025Roof Steel Purlins CLT.010Roof Cladding Installation SS 2856% Safety zone Lag >5d Lag >50% OD
CIV.100Substation Foundation ELE.100Transformer Installation FS 2135% Concrete cure + inspection Lag >5d
ARC.020Internal Partitions MEP.060HVAC Duct Installation SS 712% Zone-by-zone sequencing Lag >5d Non-FS
MEC.010Process Vessel Foundation MEC.015Vessel Mechanical Install SF 00% None on file Non-FS SF Rel (unusual)
ELE.050Underground Duct Encasement ELE.060HV Cable Energisation FS 3083% Authority energisation permit Lag >5d Lag >50% OD
CIV.060Road Base Compaction PAV.005Prime Coat Application FS 310% Density test period
COM.005Control System Wiring COM.010DCS Logic Testing SS -14−31% None on file Neg. Lag (Lead) Non-FS
STR.040Mezzanine Floor Steel ARC.030Mezzanine Floor Deck SS 1240% Parallel installation Lag >5d Non-FS
Schedule Compression Detection

200 SS+lag relationships indicate systematic schedule compression by the contractor. Key finding: 76 relationships have lags exceeding 50% of the successor's OD — effectively making them equivalent to FS relationships but masking true logic. 38 negative lags create artificial leads that may not be executable. DCMA 14-point check identifies this as schedule gaming risk.

Recommended Actions

Schedule review workshop with contractor required:

  • Convert all SS+lag >50% OD to FS relationships
  • Remove or justify all 38 negative lags
  • Challenge SF relationships — provide construction methodology
  • Require revised baseline submission by 20 Mar 2026