| ID | Activity Name | Status | OD | RD | BL Start | Act Start | BL Finish | Fcst Finish | TF | % | Resource | P | S |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.1 · Civil Works & Earthworks · 84 activities · 52% complete | |||||||||||||
| CIV.010 | Site Preparation & Clearing | Complete | 45 | 0 | 01 Jul 2025 | 01 Jul 2025 | 14 Sep 2025 | 12 Sep 2025 | 0 | 100% |
AlQahtani Lab | 0 | 1 |
| CIV.020 | Topographic Survey — Corridor Km 0–3 | Complete | 14 | 0 | 05 Jul 2025 | 05 Jul 2025 | 19 Jul 2025 | 19 Jul 2025 | 12 | 100% |
Survey Crew A | 0 | 2 |
| CIV.040 | Foundation Earthworks & Subgrade | Complete | 60 | 0 | 15 Sep 2025 | 13 Sep 2025 | 10 Nov 2025 | 15 Nov 2025 | 0 | 100% |
AlJaber Civils | 1 | 2 |
| CIV.060 | Drainage Culvert Install — Km 0–2 | Complete | 28 | 0 | 01 Nov 2025 | 01 Nov 2025 | 29 Nov 2025 | 28 Nov 2025 | 8 | 100% |
AlJaber Civils | 1 | 1 |
| CIV.080 | Box Culvert Install — Km 4+200 | In Progress | 22 | 18 | 05 Feb 2026 | 10 Feb 2026 | 26 Feb 2026 | 17 Mar 2026 | 2 | 18% |
AlJaber Civils | 1 | 3 |
| CIV.095 | Retaining Wall Backfill — Km 6 | In Progress | 18 | 14 | 10 Feb 2026 | 12 Feb 2026 | 27 Feb 2026 | 14 Mar 2026 | 4 | 22% |
AlJaber Civils | 2 | 2 |
| CIV.100 | Median Earthworks — Km 3–5 | Not Started | 20 | 20 | 01 Mar 2026 | — | 20 Mar 2026 | 20 Mar 2026 | 15 | 0% |
AlJaber Civils | 1 | 2 |
| CIV.110 | Drainage Outfall Connection | In Progress | 16 | 12 | 15 Feb 2026 | 15 Feb 2026 | 02 Mar 2026 | 12 Mar 2026 | 8 | 25% |
AlQahtani Lab | 1 | 1 |
| CIV.120 | Road Subbase Layer — Km 5–7 | Not Started | 24 | 24 | 20 Mar 2026 | — | 13 Apr 2026 | 13 Apr 2026 | 22 | 0% |
Paving Co. | 1 | 1 |
| 1.2 · Structures (Bridges & Viaducts) · 62 activities · 35% complete | |||||||||||||
| STR.010 | Bridge Pile Driving — Wadi Crossing | Complete | 35 | 0 | 15 Nov 2025 | 15 Nov 2025 | 20 Dec 2025 | 05 Jan 2026 | 0 | 100% |
Geotec KSA | 0 | 1 |
| STR.020 | Bridge Deck Formwork Install | In Progress | 55 | 28 | 18 Dec 2025 | 06 Jan 2026 | 18 Jan 2026 | 28 Mar 2026 | 0 | 49% |
Struct-Build | 1 | 1 |
| STR.035 | Precast Parapet Wall Erection | Not Started | 22 | 22 | 19 Jan 2026 | — | 10 Feb 2026 | 19 Mar 2026 | 3 | 0% |
Struct-Build | 1 | 2 |
| STR.042 | Bridge Bearing Installation | Not Started | 28 | 28 | 01 Feb 2026 | — | 01 Mar 2026 | 27 Mar 2026 | 7 | 0% |
Struct-Build | 1 | 2 |
| STR.055 | Pedestrian Underpass Structure — Km 5 | Complete | 42 | 0 | 01 Oct 2025 | 01 Oct 2025 | 12 Nov 2025 | 10 Nov 2025 | 18 | 100% |
Struct-Build | 2 | 1 |
| STR.068 | Abutment Wing Wall — N Side | In Progress | 30 | 20 | 20 Jan 2026 | 20 Jan 2026 | 19 Feb 2026 | 12 Mar 2026 | 10 | 33% |
Geotec KSA | 1 | 3 |
| STR.075 | Expansion Joint Installation | Not Started | 14 | 14 | 01 Apr 2026 | — | 15 Apr 2026 | 15 Apr 2026 | 24 | 0% |
Struct-Build | 1 | 1 |
| 1.3 · Mechanical & Electrical · 56 activities · 8% complete | |||||||||||||
| MEC.010 | Pump Station Steel Erection | Not Started | 72 | 72 | 02 Feb 2026 | — | 02 Feb 2026 | 28 Mar 2026 | 0 | 0% |
MechWork KSA | 1 | 1 |
| MEC.030 | Pump & Valve Installation | Not Started | 48 | 48 | 14 Mar 2026 | — | 14 Mar 2026 | 27 Jun 2026 | 0 | 0% |
MechWork KSA | 1 | 1 |
| ELE.010 | HV Substation Foundation | Complete | 25 | 0 | 01 Nov 2025 | 01 Nov 2025 | 26 Nov 2025 | 26 Nov 2025 | 30 | 100% |
ElecPower Co. | 0 | 2 |
| ELE.020 | Street Lighting Duct Installation | In Progress | 40 | 35 | 20 Jan 2026 | 20 Jan 2026 | 01 Mar 2026 | 04 Apr 2026 | 5 | 13% |
ElecPower Co. | 1 | 2 |
| ELE.028 | Substation Panel Cabling | In Progress | 45 | 40 | 25 Jan 2026 | 25 Jan 2026 | 10 Mar 2026 | 10 Apr 2026 | 9 | 11% |
ElecPower Co. | 2 | 1 |
| ELE.040 | Electrical Terminations & Cabling | Not Started | 38 | 38 | 22 May 2026 | — | 22 May 2026 | 17 Oct 2026 | 0 | 0% |
ElecPower Co. | 1 | 1 |
OD = Original Duration (d) · RD = Remaining Duration (d) · TF = Total Float (d) · P = Predecessor Count · S = Successor Count · Red dates indicate forecast later than baseline.