R-10: Activity Status Report (Detailed)
Data Date: 28 Feb 2026
Activity Status Report — Detailed Register
Comprehensive Activity Register Grouped by WBS Level 2 — Al Rayyan Highway Project
ProjectAl Rayyan Highway — Phase 2
Data Date28 Feb 2026
Total Activities287
Shown (filtered)42
ViewWBS Level 2
Not Started
118
41% of total
In Progress
84
29% of total
Complete
85
30% of total
Behind BL
38
finish variance >5d
Critical
23
TF = 0d
Status: Float: Discipline:
Activity Detail — All WBS Groups
ID Activity Name Status OD RD BL Start Act Start BL Finish Fcst Finish TF % Resource P S
1.1 · Civil Works & Earthworks · 84 activities · 52% complete
CIV.010Site Preparation & Clearing Complete 450 01 Jul 202501 Jul 2025 14 Sep 202512 Sep 2025 0
100%
AlQahtani Lab01
CIV.020Topographic Survey — Corridor Km 0–3 Complete 140 05 Jul 202505 Jul 2025 19 Jul 202519 Jul 2025 12
100%
Survey Crew A02
CIV.040Foundation Earthworks & Subgrade Complete 600 15 Sep 202513 Sep 2025 10 Nov 202515 Nov 2025 0
100%
AlJaber Civils12
CIV.060Drainage Culvert Install — Km 0–2 Complete 280 01 Nov 202501 Nov 2025 29 Nov 202528 Nov 2025 8
100%
AlJaber Civils11
CIV.080Box Culvert Install — Km 4+200 In Progress 2218 05 Feb 202610 Feb 2026 26 Feb 202617 Mar 2026 2
18%
AlJaber Civils13
CIV.095Retaining Wall Backfill — Km 6 In Progress 1814 10 Feb 202612 Feb 2026 27 Feb 202614 Mar 2026 4
22%
AlJaber Civils22
CIV.100Median Earthworks — Km 3–5 Not Started 2020 01 Mar 2026 20 Mar 202620 Mar 2026 15
0%
AlJaber Civils12
CIV.110Drainage Outfall Connection In Progress 1612 15 Feb 202615 Feb 2026 02 Mar 202612 Mar 2026 8
25%
AlQahtani Lab11
CIV.120Road Subbase Layer — Km 5–7 Not Started 2424 20 Mar 2026 13 Apr 202613 Apr 2026 22
0%
Paving Co.11
1.2 · Structures (Bridges & Viaducts) · 62 activities · 35% complete
STR.010Bridge Pile Driving — Wadi Crossing Complete 350 15 Nov 202515 Nov 2025 20 Dec 202505 Jan 2026 0
100%
Geotec KSA01
STR.020Bridge Deck Formwork Install In Progress 5528 18 Dec 202506 Jan 2026 18 Jan 202628 Mar 2026 0
49%
Struct-Build11
STR.035Precast Parapet Wall Erection Not Started 2222 19 Jan 2026 10 Feb 202619 Mar 2026 3
0%
Struct-Build12
STR.042Bridge Bearing Installation Not Started 2828 01 Feb 2026 01 Mar 202627 Mar 2026 7
0%
Struct-Build12
STR.055Pedestrian Underpass Structure — Km 5 Complete 420 01 Oct 202501 Oct 2025 12 Nov 202510 Nov 2025 18
100%
Struct-Build21
STR.068Abutment Wing Wall — N Side In Progress 3020 20 Jan 202620 Jan 2026 19 Feb 202612 Mar 2026 10
33%
Geotec KSA13
STR.075Expansion Joint Installation Not Started 1414 01 Apr 2026 15 Apr 202615 Apr 2026 24
0%
Struct-Build11
1.3 · Mechanical & Electrical · 56 activities · 8% complete
MEC.010Pump Station Steel Erection Not Started 7272 02 Feb 2026 02 Feb 202628 Mar 2026 0
0%
MechWork KSA11
MEC.030Pump & Valve Installation Not Started 4848 14 Mar 2026 14 Mar 202627 Jun 2026 0
0%
MechWork KSA11
ELE.010HV Substation Foundation Complete 250 01 Nov 202501 Nov 2025 26 Nov 202526 Nov 2025 30
100%
ElecPower Co.02
ELE.020Street Lighting Duct Installation In Progress 4035 20 Jan 202620 Jan 2026 01 Mar 202604 Apr 2026 5
13%
ElecPower Co.12
ELE.028Substation Panel Cabling In Progress 4540 25 Jan 202625 Jan 2026 10 Mar 202610 Apr 2026 9
11%
ElecPower Co.21
ELE.040Electrical Terminations & Cabling Not Started 3838 22 May 2026 22 May 202617 Oct 2026 0
0%
ElecPower Co.11

OD = Original Duration (d) · RD = Remaining Duration (d) · TF = Total Float (d) · P = Predecessor Count · S = Successor Count · Red dates indicate forecast later than baseline.