Critical Path Report
Longest Path Analysis & Near-Critical Activity Register — Al Rayyan Highway Project
CP Length
318d
remaining duration
CP Activities
9
on longest path
Total Float
0d
critical = TF ≤ 0
Near-Critical
14
TF 1–10 days
CP Shift
+22d
since last period
Critical Path Chain — Longest Path Sequence
CIV.010
Site Preparation & Clearing
OD: 45d
100%
CIV.040
Foundation Earthworks & Subgrade
OD: 60d
100%
STR.020
Bridge Deck Formwork Install
OD: 55d · RD: 28d
49%
MEC.010
Pump Station Steel Erection
OD: 72d
0%
MEC.030
Pump & Valve Installation
OD: 48d
0%
MEC.060
Piping Fabrication & Spool Fit
OD: 64d
0%
ELE.040
Electrical Terminations & Cabling
OD: 38d
0%
COM.010
System Pre-commissioning
OD: 30d
0%
MS.990
Mechanical Completion Milestone
Target: 15 Dec 2026
0%
Critical Path Activity Detail
| Activity ID |
Activity Name |
Status |
OD (d) |
RD (d) |
TF (d) |
% Comp |
BL Finish |
Forecast Finish |
Variance |
| CIV.010 |
Site Preparation & Clearing |
Complete |
45 |
0 |
0 |
100% |
14 Sep 2025 |
12 Sep 2025 |
+2d |
| CIV.040 |
Foundation Earthworks & Subgrade |
Complete |
60 |
0 |
0 |
100% |
10 Nov 2025 |
15 Nov 2025 |
−5d |
| STR.020 |
Bridge Deck Formwork Install |
In Progress |
55 |
28 |
0 |
49% |
18 Jan 2026 |
28 Mar 2026 |
−69d |
| MEC.010 |
Pump Station Steel Erection |
Not Started |
72 |
72 |
0 |
0% |
02 Feb 2026 |
28 Mar 2026 |
−54d |
| MEC.030 |
Pump & Valve Installation |
Not Started |
48 |
48 |
0 |
0% |
14 Mar 2026 |
27 Jun 2026 |
−105d |
| MEC.060 |
Piping Fabrication & Spool Fit |
Not Started |
64 |
64 |
0 |
0% |
18 Apr 2026 |
14 Aug 2026 |
−118d |
| ELE.040 |
Electrical Terminations & Cabling |
Not Started |
38 |
38 |
0 |
0% |
22 May 2026 |
17 Oct 2026 |
−148d |
| COM.010 |
System Pre-commissioning |
Not Started |
30 |
30 |
0 |
0% |
25 Jun 2026 |
24 Nov 2026 |
−152d |
| MS.990 |
Mechanical Completion Milestone |
Milestone |
0 |
0 |
0 |
0% |
15 Dec 2026 |
15 Dec 2026 |
— |
CP Shift Analysis
The critical path has shifted from Civil earthworks to the Mechanical package. STR.020 (Bridge Deck Formwork) is running 8 weeks late due to delayed rebar delivery from the sole-source supplier. This directly delays MEC.010 start, cascading 22 calendar days onto the mechanical sequence.
Mitigation Actions Required
- Accelerate STR.020 — deploy 2nd formwork crew by 14 Mar 2026
- Pre-order MEC.010 structural steel: 6-week lead time at risk
- Review ELE.040 predecessor logic — SS+10d lag may be compressible
- Commissioner schedule review with Owner by 20 Mar 2026
Near-Critical Activities (TF 1–10 days)
| Activity ID |
Name |
Discipline |
TF (d) |
RD (d) |
Forecast Finish |
Risk Level |
| CIV.080 | Box Culvert Installation — Km 4+200 | Civil | 2 | 18 | 17 Mar 2026 | Critical |
| STR.035 | Precast Parapet Wall Erection | Structures | 3 | 22 | 19 Mar 2026 | Critical |
| CIV.095 | Retaining Wall Backfill — Km 6 | Civil | 4 | 14 | 14 Mar 2026 | High |
| ELE.020 | Street Lighting Duct Installation | Electrical | 5 | 35 | 04 Apr 2026 | High |
| MEC.005 | Pump Station Concrete Works | Mechanical | 5 | 20 | 17 Mar 2026 | High |
| STR.042 | Bridge Bearing Installation | Structures | 7 | 28 | 27 Mar 2026 | High |
| CIV.110 | Drainage Outfall Connection | Civil | 8 | 12 | 12 Mar 2026 | High |
| ELE.028 | Substation Panel Cabling | Electrical | 9 | 40 | 10 Apr 2026 | Monitor |
| PAV.015 | Asphalt Base Course Km 3–5 | Paving | 10 | 16 | 16 Mar 2026 | Monitor |