R-06: Two-Week Lookahead Report
Data Date: 07 Jun 2025
Two-Week Lookahead Report
Al Rayyan Highway — Zone B | Window: 09 Jun – 20 Jun 2025
ProjectAl Rayyan Highway Upgrade
Look-ahead Window09 Jun – 20 Jun 2025
Zone / AreaZone B — Ch. 14+000 to 22+500
Prepared byY. Al-Rashidi (Planner)
ReviewedSite Foreman, 07 Jun 2025
Activities in Window
18
Zone B, 14 days
Clear to Proceed
13
All constraints met
Blocked — Permits
3
Awaiting road closure NOC
Blocked — Materials
2
Asphalt & HDPE pipe delayed
Critical Path Activities
6
Float = 0d
Active / On Track
At Risk / Constrained
Blocked
Complete
✓ Predecessor OK  |  ✗ Predecessor Not Met
14-Day Activity Window — Zone B
Act ID Activity Name Zone Trade Crew Pred Materials Week 1 — 09–13 Jun 2025 Wknd Week 2 — 16–20 Jun 2025 Wknd Notes
M
9
T
10
W
11
T
12
F
13
Sa Su M
16
T
17
W
18
T
19
F
20
Sa Su
ARH.B1010 Subgrade Compaction Ch.14+000–15+500 B-1 Civil Crew 3 Ready CP — on track
ARH.B1020 Sub-base Layer 1 — Crushed Aggregate B-1 Civil Crew 3 Ready Follows B1010
ARH.B1030 Kerb & Channel — Ch.14+200–16+000 B-1 Civil Crew 5 Ready 7d duration
ARH.B2010 Lane Closure — Carriageway A (North) B-2 Traffic Blocked PERMIT PENDING PERMIT PENDING NOC submitted 31 May. Est. approval: 18 Jun
ARH.B2020 Carriageway A Milling & Removal B-2 Paving Crew 1 Blocked DEPENDS ON B2010 — BLOCKED BY NOC Cannot start until lane closure approved
ARH.B2030 Asphalt Base Course — Carriageway A B-2 Paving Crew 1 No Stock BLOCKED — PERMIT + MATERIALS Asphalt plant delivery: est. 20 Jun
ARH.B3010 Storm Drainage — Box Culvert Install B-3 Civil Crew 4 Ready CP activity
ARH.B3020 Drainage Backfill & Compaction B-3 Civil Crew 4 Ready Follows B3010
ARH.B3030 HDPE Drainage Pipe — Ch.18+000–20+000 B-3 Civil Crew 6 Delayed HDPE pipe delivery: 18 Jun (est.)
ARH.B4010 Traffic Signal Foundation — Int. 7 B-4 Civil Crew 7 Ready 2d pour + cure
ARH.B4020 Traffic Signal Pole Erection — Int. 7 B-4 Electrical SC-E2 Ready Subcon SC-E2
ARH.B4030 Cable Duct Installation — Int. 7 B-4 Electrical SC-E2 Ready 3d continuous
ARH.B5010 Median Barrier — Precast Concrete (600m) B-5 Civil Crew 2 Ready CP — 7d, 100 units/day
ARH.B5020 Road Marking — Temp Paint (Zone B) B-5 Road Mkng SC-M1 Ready Night work only
ARH.B6010 Streetlight Foundation — Wk1 Batch (12 No.) B-6 Electrical SC-E1 Ready Batch 1 of 4
ARH.B6020 Streetlight Column & Luminaire Wk1 B-6 Electrical SC-E1 Ready After cure period
ARH.B7010 Survey Check & As-Built — Zone B Wk1 B-All Survey Survey N/A Friday EOW check

Shaded rows: Red = blocked, Yellow = awaiting materials. Weekend columns (Sa/Su) are non-working. Crew codes: Crew 1–7 = direct workforce; SC-E1/E2 = electrical subcontractors; SC-M1 = marking subcontractor.

Lookahead Summary & Actions Required

3 activities blocked by NOC permit (B2010, B2020, B2030): The Road Closure NOC for Carriageway A was submitted to the Traffic Department on 31 May 2025. Expected approval: 18 Jun 2025. If approved on schedule, milling can start 19 Jun (late in W2). Action: Y. Al-Rashidi to follow up with Traffic Dept by 09 Jun and escalate if no response by 12 Jun.

2 activities awaiting materials (B2030, B3030): HDPE 600mm pipe (120m) delivery from local supplier confirmed for 18 Jun — late start to B3030 acceptable, no float impact. Asphalt base course material for B2030 depends on NOC clearance first; plant availability confirmed for 2 weeks' notice.

Critical path activities (B1010, B3010, B5010): All three are clear to proceed and resource-confirmed. Crew 3 and Crew 4 must not be diverted to Carriageway A rework during Wk1.