R-05: Weekly Progress Report — Week 23
Data Date: 06 Jun 2025
Weekly Progress Report — Week 23
ERP Implementation Phase 2 | Period: 02 Jun – 06 Jun 2025
ProjectERP Implementation Phase 2
Report WeekWk 23 (02–06 Jun 2025)
Project PhaseBuild & Configure
PMR. Kowalski, PMP
Baseline Finish30 Nov 2025
% Complete (Physical)
47.3%
BL target this week: 51.0%
Schedule Performance (SPI)
0.93
3.7% behind schedule
SPI 0.93
Cost Performance (CPI)
1.04
4% under budget (favourable)
CPI 1.04
Activities Completed (Week)
3
Planned: 4 this week
Activities in Progress
14
2 behind plan
Activities Completed This Week (3 of 4 Planned)
Activity ID Activity Name WBS BL Finish Actual Finish Variance Status
ERP.2100 Finance Module — Chart of Accounts Configuration ERP2.FIN 30 May 2025 02 Jun 2025 +3d Late Finish
ERP.2215 Procurement — Vendor Master Data Migration ERP2.PROC 04 Jun 2025 04 Jun 2025 0d On Time
ERP.2310 HR Module — Payroll Rules Configuration ERP2.HR 06 Jun 2025 05 Jun 2025 -1d Early

ERP.1480 (Integration Testing Prep) was planned for completion this week but has been deferred to Wk24 due to environment setup delays.

Activities Started This Week (2)
Activity ID Activity Name BL Start Actual Start Var
ERP.2400 Asset Mgt — Fixed Asset Register Build 02 Jun 2025 02 Jun 2025 0d
ERP.2500 Inventory — Item Master Cleanse & Load 04 Jun 2025 06 Jun 2025 +2d
Planned Next Week (Wk 24) — 5 Activities
Activity ID Activity Name BL Start BL Finish Duration
ERP.1480 Integration Testing Prep 09 Jun 2025 13 Jun 2025 5d
ERP.2410 Depreciation Schedule Setup 09 Jun 2025 10 Jun 2025 2d
ERP.2510 Inventory Valuation Method Config 09 Jun 2025 11 Jun 2025 3d
ERP.3010 Wk24 Module Integration Test — Cycle 1 10 Jun 2025 13 Jun 2025 4d
ERP.3020 Defect Log Review — Finance & HR 12 Jun 2025 13 Jun 2025 2d
Milestone Status
Complete MS-01 — Phase 2 Kickoff & Planning Complete BL: 14 Jan 2025 Act: 14 Jan 2025 0d
Complete MS-05 — Build Phase Start Confirmed BL: 03 Mar 2025 Act: 03 Mar 2025 0d
Forecast MS-10 — System Integration Test Commence BL: 30 Jun 2025 FC: 30 Jun 2025 0d
At Risk MS-15 — User Acceptance Testing Sign-Off BL: 31 Aug 2025 FC: 19 Sep 2025 +19d
Forecast MS-20 — ERP Go-Live (Phase 2 Modules) BL: 30 Nov 2025 FC: 19 Dec 2025 +19d
Key Risks & Issues This Week
Risk: SIT Environment Not Available (HIGH)

ID: R-024 | Owner: T. Bakker (IT Infra) — The System Integration Testing environment has a 3-week delay due to cloud provisioning issues with the new Azure tenant. SIT was planned to start 09 Jun 2025. Current forecast start: 30 Jun 2025. This is the primary driver of the +19d slippage on MS-15 (UAT sign-off) and is tracking to delay the Go-Live milestone by 19 calendar days unless recovery plan is implemented.

Mitigation: PM has escalated to CIO. Parallel-pathing of UAT prep activities where possible. Decision on compressed UAT cycle (2 weeks vs 3 weeks) to be made by 13 Jun 2025.

Issue: Finance Module Config Rework (LOW)

ID: I-018 | Owner: C. Vasquez (Functional Lead) — Chart of Accounts config required 2 iterations due to late requirement change from client Finance Director. Resolved and closed this week. No net schedule impact beyond 3-day late finish on ERP.2100.

Management Summary
Project Controls Summary — Week 23

Project is 3.7% behind schedule (SPI = 0.93) but 4% under budget (CPI = 1.04). The schedule variance is entirely attributable to the IT infrastructure risk (R-024). The underlying build and configuration work is performing to plan — 3 of 4 activities completed this week, with the fourth deferred pending environment readiness.

The forecast Go-Live date has been revised to 19 Dec 2025 (from 30 Nov 2025). This is within the contractual tolerance of 30 calendar days late without penalty. A recovery schedule will be presented at the Steering Committee on 20 Jun 2025. Compressed UAT cycle and parallel module deployment are the two levers under evaluation.