R-04: WBS Dictionary Report
Data Date: 28 Feb 2026
WBS Dictionary Report
Nordic Wind Farm EPC — Levels 1–4 | Baseline BL1
ProjectNordic Wind Farm (NWF-EPC)
P6 Project IDNWF-2025-EPC
ClientNordic Green Energy AS
WBS Levels4
Total Nodes47
Total Budget€ 284,500,000
Level 1 Nodes
1
Project root
Level 2 (Disciplines)
6
Major discipline branches
Level 3 Nodes
18
Work packages
Level 4 Nodes
22
Cost accounts
Total Activities
3,214
Across all nodes
WBS Dictionary — Full Hierarchy
WBS Code Name & Scope Resp. Manager Budget (€) Activities Milestones Level
NWF Nordic Wind Farm — EPC Project
Full EPC delivery of 42-turbine onshore wind farm, 280 MW installed capacity. Includes civil, structural, electrical, mechanical, erection, and commissioning scope.
E. Svensson (PM) 284,500,000 3,214 88 L1
NWF.CIV Civil & Geotechnical
Site preparation, access roads, turbine foundation excavation and backfill, cable trenching, substation civil works, drainage.
H. Magnusson 48,200,000 612 14 L2
NWF.CIV.010 Site Clearance & Earthworks
Tree felling, topsoil strip, bulk earthworks for 42 turbine pads and 18 km access road.
H. Magnusson 9,400,000 148 3 L3
NWF.CIV.010.01 Topsoil Strip & Stockpile H. Magnusson 1,800,000 36 1 L4
NWF.CIV.010.02 Access Road Construction (18 km) H. Magnusson 5,200,000 74 1 L4
NWF.CIV.020 Turbine Foundations (42 No.)
Gravity pad foundations, reinforced concrete. Avg 500m³ concrete per turbine. Includes piling where ground conditions require.
H. Magnusson 21,600,000 294 6 L3
NWF.CIV.020.01 Foundation Excavation — All Turbines H. Magnusson 4,200,000 84 2 L4
NWF.CIV.020.02 Rebar, Formwork & Concrete Pour H. Magnusson 14,800,000 168 2 L4
NWF.STR Structural Steel & Towers
Supply and erection of steel lattice meteorological mast, substation structural steelwork, turbine tower assembly preparation and bolt tightening.
B. Eriksson 12,800,000 284 8 L2
NWF.STR.030 Turbine Tower Erection & Grouting
Tower sections unload, stage, and erect. Grouting of anchor bolt cage. Torque checking per OEM specification.
B. Eriksson 9,600,000 210 6 L3
NWF.ELEC Electrical & Grid Connection
Inter-array 33kV cabling (120 km), onshore substation 132/33kV, grid connection works, SCADA system. Includes all switchgear and transformer supply.
L. Petersen 74,400,000 698 20 L2
NWF.ELEC.040 Inter-Array Cable Installation
Supply and installation of 33kV XLPE underground cables. Includes cable drum delivery logistics, trenching, jointing, and testing.
L. Petersen 28,200,000 312 8 L3
NWF.ELEC.050 Onshore Substation — 132/33kV
Contractor-designed substation. Two 100 MVA transformers, GIS switchgear, protection relays, SCADA integration. Grid connection agreement with TSO.
L. Petersen 38,600,000 286 10 L3
NWF.ELEC.050.01 Transformer T1 & T2 Supply & Install L. Petersen 18,400,000 84 4 L4
NWF.ELEC.050.02 GIS Switchgear & Protection L. Petersen 12,200,000 124 4 L4
NWF.MECH Turbine Supply & Mechanical Erection
Supply of 42 × 6.6 MW direct drive turbines (OEM: Vestas V162). Includes nacelle lifting, blade assembly, rotor installation, hub, and mechanical commissioning.
T. Halvorsen 118,400,000 882 28 L2
NWF.MECH.060 Turbine Delivery & Logistics
Component delivery scheduling, abnormal load route permits, port off-load, temporary storage, and component staging at turbine pads.
T. Halvorsen 8,200,000 126 8 L3
NWF.MECH.070 Nacelle & Blade Erection (42 WTG)
Main crane mobilisation, tower top lifting, nacelle installation, blade assembly on ground, 3-blade rotor lift. One turbine per day at peak.
T. Halvorsen 22,400,000 504 14 L3
NWF.COMM Commissioning & Grid Energisation
Electrical commissioning, mechanical commissioning, OEM turbine commissioning, performance testing (10-day test per IEC), grid connection energisation, PAC issuance.
A. Dahl 18,200,000 512 14 L2
NWF.PMC Project Management & Controls
Overall EPC project management, engineering oversight, document control, HSE management, cost control, schedule control, client reporting, and contract administration.
E. Svensson 12,500,000 226 4 L2

Showing 22 of 47 nodes. Full 4-level dictionary includes 22 Level 4 cost accounts. Budget figures exclude client-supplied items and contingency (€ 18.2M held separately).

Dictionary Notes

WBS structure follows the EPC phasing: Engineering → Procurement → Construction → Commissioning with discipline branches at Level 2. NWF.MECH represents 41.6% of total budget and is the schedule-driving discipline, dependent on NWF.CIV.020 (foundations) for turbine erection access. The critical milestone is first power to grid (NWF.COMM, Q4 2027) which has a regulatory deadline under the grid connection agreement with the national TSO.