Program Manager Dashboard — Project Atlas
IT Program · 6 Projects · Generated: 01 Mar 2026 08:15 AM
Program Projects
6
Software releases
Program Budget
$48M
EAC: $49.6M (+3.3%)
Avg SPI
0.96
2 projects below 0.90
Resource Conflicts
3
QA team peak — Apr
Cross-Project Deps
12
3 at-risk, 1 critical
Program End Date
15 Sep 26
BL: 31 Aug 26 (+15d)
Complete / On Track
At Risk
Late / Critical
| Resource |
Project A |
Project B |
Period |
Sev. |
| QA Team (3) |
Atlas Core |
Atlas Data |
Apr 5–18 |
High |
| DevOps Lead |
Atlas Mobile |
Atlas Security |
Mar 28–Apr 10 |
Med |
| DB Architect |
Atlas Data |
Atlas Integr. |
May 12–Jun 5 |
Med |
QA Team bottleneck — Peak Apr 5–18
QA team (3 FTE) requested by 2 projects simultaneously. Recommended: stagger Atlas Core UAT to Apr 20. Impact: +5 days Atlas Core go-live.
| Project |
SPI |
CPI |
% Comp |
Status |
Next Milestone |
| Atlas Core |
0.94 |
1.02 |
68% |
Watch |
UAT Sign-off · 15 May |
| Atlas Mobile |
1.02 |
0.99 |
74% |
On Track |
App Store · 25 May |
| Atlas Data |
0.88 |
0.93 |
42% |
At Risk |
ETL Framework · 22 Mar |
| Atlas Security |
0.97 |
1.01 |
81% |
On Track |
Pen Test · 10 Mar |
| Atlas Integration |
0.91 |
0.96 |
38% |
Watch |
API Cert · 1 May |
| Atlas Reports |
1.00 |
1.03 |
55% |
On Track |
Dashboard Del. · 15 May |
Oct 25NovDecJanFebMarAprMay
BCWS
BCWP
ACWP
Forecast
BCWP: $25.8M
ACWP: $27.4M
CV: −$1.6M
SV: −$1.1M
EAC: $49.6M
| From Project |
Activity (Predecessor) |
To Project |
Activity (Successor) |
Rel. |
Planned Hand-off |
Forecast |
Var (d) |
Status |
| Atlas Core |
API v2.0 Finalized |
Atlas Mobile |
Mobile SDK Integration |
FS |
20 Mar 2026 |
20 Mar 2026 |
0 |
On Track |
| Atlas Data |
Data Warehouse Schema Lock |
Atlas Reports |
Dashboard Data Binding |
FS |
31 Mar 2026 |
15 Apr 2026 |
+15 |
At Risk |
| Atlas Security |
SSO Module Deployed |
Atlas Core |
User Authentication Integration |
FS |
15 Apr 2026 |
15 Apr 2026 |
0 |
On Track |
| Atlas Data |
ETL Pipelines — Production |
Atlas Integration |
Real-Time Data Feed Config. |
FS |
10 Apr 2026 |
25 Apr 2026 |
+15 |
Critical |
| Atlas Integration |
SAP Connector Certified |
Atlas Core |
ERP Data Sync Feature |
SS |
20 Jun 2026 |
20 Jun 2026 |
0 |
On Track |
| Atlas Core |
Performance Load Test — Pass |
Atlas Reports |
Reporting Layer Production Deploy |
FS |
1 Jul 2026 |
5 Jul 2026 |
+4 |
Watch |
Critical Cross-Project Risk:
Atlas Data ETL delay (+15d) will cascade into Atlas Integration start, which then delays Atlas Integration's SAP certification and could push program end date by 15 days to 30 Sep 2026.